FIR18-00629
| INSP-Final Inspection | 5/1/2020 | 5/5/2020 | 5/6/2020 10:16:53 AM | P | CANC |
|
|
please come after 2:30 if possible. this is for the forward flow for the new BFP. Phone #: ###-#### Inspection requested via web by Connie Danes
|
FIR19-00769
| INSP-Sprinkler Rough-in | 5/4/2020 | 5/5/2020 | 5/5/2020 12:27:45 PM | P | PASS |
|
|
The 24 hour air test was witnessed for both dry systems.
This Inspection will be to finish the 24-hour air test started on Monday afternoon. Please give Jim Lewis a call to schedule the inspection time. ###-#### Phone #: ###-#### Inspection requested via web by Joshua Hansen
|
BLD20-00298
| FIRE-Final Inspection | 5/4/2020 | 5/5/2020 | 5/5/2020 10:28:28 AM | P | PASS |
|
|
Life safety passed. See load reduction approved by the building and fire dept.
Jake Phone #: ###-####
|
FIR19-00783
| INSP-Sprinkler Rough-in | 5/5/2020 | 5/5/2020 | 5/5/2020 10:06:31 AM | P | FAIL |
|
|
Need as-builts showing the pipe routing changes and pipe size changes, repair the tenting in two spots, relocate one overspaced pendant in the breezeway and repir two hangers on the first floor.
screened // Tanner Phone #: ###-####
|
BLD20-00145
| FIRE-Final Inspection | 5/4/2020 | 5/5/2020 | 5/5/2020 8:58:54 AM | A | PASS |
|
|
Life safety passed. if you have any questions you can call me at ###-####
thanks Mike Teeter Phone #: ###-#### Inspection requested via web by Mike Teeter
|
FIR19-00785
| INSP-Final Inspection | 5/5/2020 | 5/5/2020 | 5/5/2020 12:00:00 AM | P | CANC |
|
|
screened // Tanner Phone #: ###-####
|
BLD20-00298
| FIRE-Final Inspection | 5/4/2020 | 5/5/2020 | 5/4/2020 11:19:02 AM | P | CANC |
|
|
Jake Phone #: ###-####
|