BLD11-00519
| FIRE-Final Inspection | 6/10/2013 | 6/10/2013 | 6/10/2013 3:42:21 PM | P | CANC |
|
|
Per Jeremiah the project is not ready for inspection. Will be rescheduled for inspection on underground supply piping to the fire sprinkler system.
|
BLD13-00996
| FIRE-Conference | 6/10/2013 | 6/10/2013 | 6/10/2013 3:12:20 PM | P | DONE |
|
|
The project superintendant and I discussed general life safety requirements. We also discussed problems with the sprinkler coverage at the new soffits and possible fire alarm modifications being needed due to new wall arrangements.
|
FIR13-00218
| INSP-Sprinkler Rough-in | 6/10/2013 | 6/10/2013 | 6/10/2013 3:09:11 PM | P | FAIL |
|
|
javier and I started the inspection but I found not all of the heads as shown on the plans have been installed and some of the pendants installed are blocked by signage/racking at the new soffits. Also I looked at some work that is not shown on the plans.
|
BLD13-01430
| FIRE-Final Inspection | 6/10/2013 | 6/10/2013 | 6/10/2013 11:05:21 AM | P | PASS |
|
|
life safety passed
|