FIR11-00543
| INSP-Sprinkler Rough-in/Hydro | 6/20/2012 | 6/20/2012 | 6/20/2012 3:45:01 PM | P | PASS |
|
|
Chiller room underground hydro test passed.
|
FIR09-00510
| FIR-Aging Inspection | 6/20/2012 | 6/20/2012 | 6/20/2012 3:34:36 PM | | NR |
|
|
Per Matt this project is slowing moving along.
|
FIR12-00116
| INSP-Sprinkler Rough-in/Hydro | 6/19/2012 | 6/20/2012 | 6/20/2012 2:21:03 PM | P | PASS |
|
|
24 hour air test passed for the pre-action system
|
FIR11-00543
| INSP-Sprinkler Rough-in | 6/19/2012 | 6/20/2012 | 6/20/2012 1:42:35 PM | A | PASS |
|
|
Rough In inspection in the attic passed for the most part. It appears that some heads are overspaced from walls are too close together and possibly too far down from the deck. The data sheets for the "Attic" heads was not available on site. The fitter will get data sheet and double check noted items and I will verify at a follow up inspection. I also noted two areas, both at the very east end of the attic, where coverage is lacking.
|