Inspections for the day of: Friday, June 21, 2019.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR19-00380 INSP-Sprinkler Rough-in6/21/20196/21/20196/21/2019 11:56:12 AMPPASS
Rough-in passed. Piping can be covered


Contact Scott Carter ###-#### 30 min prior to RTC Insp start please.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
BLD11-02634 FIRE-Final Inspection6/20/20196/21/20196/21/2019 11:17:54 AMAPASS
life safety passed

Ray Phone #: ###-####
FIR19-00457 INSP-Sprinkler Rough-in6/20/20196/21/20196/21/2019 9:46:30 AMACANC
Please meet Anthony first thing if possible. Call when on your way. Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
NAF19-00023 INSP-Final6/20/20196/21/20196/21/2019 9:37:00 AMADONE
life safety passed

Call prior to going Phone #: 2084077853 >> Inspection requested via mobile web by Laura Schulte
FIR18-00698 INSP-Sprinkler Rough-in/Hydro6/20/20196/21/20196/21/2019 9:18:00 AMAPASS
Underground hydro test witnessed with no visible loss of pressure.

Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
FIR18-00697 INSP-Sprinkler Rough-in/Hydro6/20/20196/21/20196/21/2019 9:17:06 AMAPASS
Underground hydro test witnessed with no visible loss of pressure.

Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
FIR18-00699 INSP-Sprinkler Rough-in/Hydro6/20/20196/21/20196/21/2019 7:53:17 AMACANC
Cancel per Gabe Garduno
FIR18-00699 INSP-Supply line flush6/20/20196/21/20196/21/2019 7:52:54 AMACANC
Cancel per Gabe Garduno