Inspections for the day of: Monday, July 16, 2018.
Number of inspections: 4
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR18-00012 INSP-Sprinkler Rough-in7/11/20187/16/20187/16/2018 1:37:10 PMAFAIL
As-builts need to be approved showing the pipe routing changes prior to a cover inspection being requested.


Phone #: ###-#### Inspection requested via web by Stan Beus
BLD17-01277 FIRE-Final Inspection7/13/20187/16/20187/16/2018 10:20:30 AMPPASS
life safetyu passed

Herb ###-####
BLD18-02363 FIRE-Final Inspection7/13/20187/16/20187/16/2018 9:08:46 AMAPASS
Life safety passed

Abdi Phone #: ###-####
BLD17-00339 FIRE-Final Inspection7/13/20187/16/20187/16/2018 8:39:41 AMAPART
A temporary for life safety is being given until the Engineering Room is complete. The project related fire alarm permit will need to be finaled as well.

Ross is the super. Last item to be reviewed is ceiling tile. Thank you! Phone #: ###-#### Inspection requested via web by Jackie Phelps