FIR18-00801
| INSP-Final Inspection | 7/17/2019 | 7/17/2019 | 7/18/2019 7:50:50 AM | P | FAIL |
|
|
All items tested except for the kitchen hood interconnect.
Brandon- Phone #: ###-####
|
BLD19-01077
| FIRE-Final Inspection | 7/17/2019 | 7/17/2019 | 7/18/2019 6:26:21 AM | P | PART |
|
|
Life safety passed for the south side tennt space of the remodel work.
Phone #: ###-#### Inspection requested via web by Gerome Fries
|
FIR18-00886
| INSP-Sprinkler Rough-in | 7/17/2019 | 7/17/2019 | 7/17/2019 2:01:15 PM | P | PASS |
|
|
See the city approved plans for additional rooms marked "ok" where piping is ok for cover.
Contact Noemi Carrero - ###-#### 30 Min prior to RTC Insp start please
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
FIR18-00525
| INSP-Sprinkler Rough-in/Hydro | 7/16/2019 | 7/17/2019 | 7/17/2019 1:27:07 PM | P | PASS |
|
|
Overhead hydro test for both systems passed.
Cole Bierman is the contact for this overhead hydro. He is requesting it for the 1st and 2nd floors. Thank you for your help. Have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR19-00315
| INSP-Final Inspection | 7/16/2019 | 7/17/2019 | 7/17/2019 1:26:35 PM | P | PASS |
|
|
Permit finaled
Contact is Dan. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
FIR19-00510
| INSP-Final Inspection | 7/17/2019 | 7/17/2019 | 7/17/2019 12:29:46 PM | P | CANC |
|
|
To be canceled per contact. Phone #: ###-#### Inspection requested via web by Kristin Dolan
|
NAF19-00065
| INSP-Sprinkler Rough-in/Hydro | 7/16/2019 | 7/17/2019 | 7/17/2019 12:13:25 PM | P | PASS |
|
|
Overhead hydro test passed. Overhead rough-in passed. Piping can be covered.
Contact: Leon Taylor Phone #: ###-#### Inspection requested via web by Hunter Fillmore
|
NAF18-00128
| INSP-Final | 7/15/2019 | 7/17/2019 | 7/17/2019 11:35:10 AM | P | CANC |
|
|
Cancel per contractor. Water connection not done yet.
Call prior to going Phone #: 2084212181 >> Inspection requested via mobile web by Brian Rumple
|
FIR18-00886
| INSP-Sprinkler Rough-in | 7/16/2019 | 7/17/2019 | 7/17/2019 10:10:35 AM | A | PASS |
|
|
See the city approved plans with areas marked "ok" where piping is ok for cover.
Contact Noemi Carrero - ###-#### 30 Min prior to RTC Insp start please
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
NAF18-00086
| INSP-Sprinkler Rough-in | 7/17/2019 | 7/17/2019 | 7/17/2019 9:58:12 AM | A | PASS |
|
|
The 4th floor piping is ok for cover. No other items ready to be looked at from the previous inspection. I noted that plan mods have not been done yet.
Contact Andrew Larson ###-#### 30 min prior to Unit #5 RTC insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
FIR19-00383
| INSP-Final Inspection | 7/16/2019 | 7/17/2019 | 7/17/2019 9:05:51 AM | A | PART |
|
|
Phase 1 of work complete. (south side)
Phone #: ###-#### Inspection requested via web by Sam Ball
|
FIR19-00281
| INSP-Sprinkler Rough-in | 7/16/2019 | 7/17/2019 | 7/17/2019 8:25:12 AM | A | PASS |
|
|
Room 501 sprinkler piping is ok for cover.
Contact Tanner Loomis ###-#### for RTC Insp on Rm 501 only.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
FIR18-00701
| INSP-Final Inspection | 7/16/2019 | 7/17/2019 | 7/17/2019 8:15:12 AM | A | PASS |
|
|
Permit finaled.
MIKE Phone #: ###-####
|
FIR19-00440
| INSP-Sprinkler Rough-in | 7/16/2019 | 7/17/2019 | 7/17/2019 7:51:07 AM | A | PASS |
|
|
The two thrust blocks are poured so the remaining piping is ok for cover.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
FIR19-00510
| INSP-Final Inspection | 7/15/2019 | 7/17/2019 | 7/17/2019 7:28:51 AM | A | CANC |
|
|
I spoke to the installing electrian at another job site and he had the new pull stations in his work truck not installed yet. All devices need installed and pretested prior to a final inspection being scheduled.
Call 30 minutes prior. Phone #: ###-#### Inspection requested via web by Kristin Dolan
|
NAF19-00065
| INSP-Sprinkler Rough-in/Hydro | 7/16/2019 | 7/17/2019 | 7/16/2019 12:00:00 AM | P | FAIL |
|
|
Failed hydro-did not maintain pressure. Dropped 20 psi in 2 hours. Not ready for rough in, no small docs or stamped prints on site.
Contact: Leon Taylor Phone #: ###-#### >> Inspection requested via web by Hunter Fillmore
|