Inspections for the day of: Tuesday, July 23, 2019.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD18-02281 FIRE-Final Inspection7/22/20197/23/20197/24/2019 9:30:54 AMAFAIL
Provide single action hardware on the two store front doors as discussed. Fire alarm has been addressed.

Mark Phone #: ###-####
FIR19-00350 INSP-Final Inspection7/23/20197/23/20197/23/2019 2:04:08 PMPPASS
permit finaled
BLD19-00521 FIRE-Final Inspection7/23/20197/23/20197/23/2019 1:15:59 PMPCANC
To be rescheduled per Josh-please call when on way so can meet with you Phone #: ###-####
BLD19-01815 FIRE-Final Inspection7/23/20197/23/20197/23/2019 12:50:36 PMAPASS
Life safety passed

Jim Wellman Phone #: ###-#### Inspection requested via web by Jim Wellman
NAF19-00005 INSP-Final7/22/20197/23/20197/23/2019 12:49:37 PMPFAIL
I left voice messages and went to the job site but could not make contact. No inspection performed.

ll prior to going Phone #: 2088699723 >> Inspection requested via mobile web by Brandon Mc Curdy
FIR19-00397 INSP-Final Inspection7/22/20197/23/20197/23/2019 12:32:12 PMAPASS
Permit finaled

Kenny Caldwell is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
FIR19-00380 INSP-Final Inspection7/22/20197/23/20197/23/2019 12:15:56 PMAPASS
Permit finaled

Contact Scott Carter ###-#### 30 min prior to Final Insp start please.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
FIR19-00440 INSP-Sprinkler Rough-in/Hydro7/23/20197/23/20197/23/2019 12:15:13 PMPPASS
The underground supply line hydro test was witnessed.

Phone #: ###-#### Inspection requested via web by Matthew Lewis
FIR19-00392 INSP-Final Inspection7/22/20197/23/20197/23/2019 10:54:19 AMAPASS
Permit finaled. Phone #: ###-#### Inspection requested via web by Jeff Packham
FIR19-00350 INSP-Alarm Testing7/20/20197/23/20197/23/2019 10:53:55 AMAPASS
Needs to be scheduled as a final. Phone #: ###-#### Inspection requested via web by John Lopez
FIR18-00931 INSP-Final Inspection7/17/20197/23/20197/23/2019 10:52:24 AMAFAIL
Lee performed inspection and found that inspeciton could not be performed due to notification in the sleeping rooms not being addressed.

Ray McQueen, inspecting technician Phone #: ###-#### Inspection requested via web by Rose PetersonRay McQueen, inspecting technician Phone #: ###-#### Inspection requested via web by Rose Peterson
FIR18-00496 INSP-Final Inspection7/17/20197/23/20197/23/2019 10:51:55 AMAFAIL
Lee performed inspection and found that inspeciton could not be performed due to notification in the sleeping rooms not being addressed.

Ray McQueen, inspecting technician Phone #: ###-#### Inspection requested via web by Rose Peterson
NAF18-00124 INSP-Sprinkler Rough-in/Hydro7/22/20197/23/20197/23/2019 10:49:17 AMAPASS
Underground supply line hydro test witnessed.

Call prior to going Phone #: 2088105425 >> Inspection requested via mobile web by Tyler Bradley