Inspections for the day of: Wednesday, July 24, 2019.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR19-00482 INSP-Final Inspection7/24/20197/24/20197/24/2019 2:54:41 PMPFAIL
The new notification circuit is not working.

Hi Troy This is the Hampton Inn Spectrum Hotel. I will call you this morning to set up an inspection this afternoon. Thanks Mike Timmerman. Phone #: ###-#### Inspection requested via web by Michael Timmerman
GRD18-00042 FIRE-Final Inspection7/23/20197/24/20197/24/2019 2:53:41 PMPPASS
Life safety passed

Josh Phone #: ###-####
FIR19-00527 INSP-Sprinkler Rough-in7/23/20197/24/20197/24/2019 2:49:38 PMAPASS
Rough-in passed. Piping can be covered.

Call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
BLD18-01425 FIRE-Final Inspection7/22/20197/24/20197/24/2019 1:32:13 PMPPART
A temporary for life safety is being given until the knox box is mounted, all signage mounted (Ox tank and fire doors), bollards installed and exit discharge lights tested as discussed.

Zach Phone #: ###-####
FIR19-00463 INSP-Sprinkler Rough-in7/23/20197/24/20197/24/2019 11:44:32 AMAPASS
Rough-in passed. Piping is ok to cover.

Phone #: ###-#### Inspection requested via web by Sam Ball
NAF18-00124 INSP-Sprinkler Rough-in/Hydro7/23/20197/24/20197/24/2019 11:29:50 AMAPART
The overhead 200lb hydro failed for both wet systems due to visible loss on the guages but the dry system passed with no visible loss at the guage.

Call prior to going Phone #: 2088105425 >> Inspection requested via mobile web by Tyler
GRD18-00042 GRD-Other7/23/20197/24/20197/23/2019 12:00:00 AMPCANC
Josh Phone #: ###-####