Inspections for the day of: Thursday, August 29, 2019.
Number of inspections: 21
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR19-00616 INSP-Sprinkler Rough-in8/29/20198/29/20198/29/2019 3:05:41 PMPPASS
Rough-in passed. Piping can be covered. Per the general contractor the restroom walls will be extended to the ceiling. Plans are on site Phone #: ###-#### Inspection requested via web by Jonathan LaFond
BLD18-00103 FIRE-Final Inspection8/29/20198/29/20198/29/2019 3:02:57 PMPFAIL
Provide knox box, provide sheetrock in closets as discussed and provide second floor signage.

Phone #: ###-#### Inspection requested via web by Andy Thompson
FIR19-00433 INSP-Final Inspection8/29/20198/29/20198/29/2019 2:04:58 PMPPASS
Permit finaled. Asbuilts approved, Troy said he would approve once as builts were approved. No inspection needed Phone #: ###-#### Inspection requested via web by Kristin Dolan
FIR19-00436 INSP-Final Inspection8/29/20198/29/20198/29/2019 2:04:31 PMPPASS
Permit finaled. Asbuilts approved, Troy said he would approve once as builts were approved. No inspection needed Phone #: ###-#### Inspection requested via web by Kristin Dolan
FIR19-00435 INSP-Final Inspection8/29/20198/29/20198/29/2019 1:56:13 PMPPASS
Permit finaled. Asbuilts approved, Troy said he would approve once as builts were approved. No inspection needed Phone #: ###-#### Inspection requested via web by Kristin Dolan
FIR19-00434 INSP-Final Inspection8/29/20198/29/20198/29/2019 1:55:50 PMPPASS
Permit finaled. Asbuilts approved, Troy said he would approve once as builts were approved. No inspection needed Phone #: ###-#### Inspection requested via web by Kristin Dolan
FIR19-00033 INSP-Final Inspection8/29/20198/29/20198/29/2019 1:55:15 PMPPASS
Permit finaled. Nick Phone #: ###-####
FIR19-00060 INSP-Final Inspection8/29/20198/29/20198/29/2019 1:54:36 PMPPASS
Permit finaled. Nick Phone #: ###-####
FIR19-00059 INSP-Final Inspection8/29/20198/29/20198/29/2019 1:51:47 PMPPASS
Permit finaled. Nick Phone #: ###-####
BLD18-00104 FIRE-Final Inspection8/29/20198/29/20198/29/2019 1:49:08 PMPPASS
life safety passed. Phone #: ###-#### Inspection requested via web by Andy Thompson
BLD18-00102 FIRE-Final Inspection8/29/20198/29/20198/29/2019 1:46:55 PMPPASS
Life safety passed. Phone #: ###-#### Inspection requested via web by Andy Thompson
BLD19-01972 FIRE-Final Inspection8/28/20198/29/20198/29/2019 1:06:46 PMPPASS
Life safety passed. A suite number is to be provided prior to a building inspection as discussed. Jim Phone #: ###-#### Inspection requested via web by Jim Wellman
FIR19-00478 INSP-Sprinkler Rough-in8/29/20198/29/20198/29/2019 1:05:44 PMPFAIL
As-builts or plan mods are needed showing the piping routing changes (additional fittings), per the data sheet for the sidewall heads the min. mounting distance from the ceiling 4" but the heads have been installed at 3 1/2". Also the sidewall heads have a max distance to be mounted off a wall and that has been exceeded. Verification needs to be provided that shows the heads have been installed per their listing. I noted the center line in the garage has no wall behind the sidewall heads again is this listed. I will need verification from the state that sprinkler coverage is not needed in the closet close to the riser. I will need to see the tenting where the piping passes above the Kitchen cabinets. I have not looked at any of the fire pump/tank items. Contact: Ricky Sullivan Phone #: ###-#### Inspection requested via web by Hunter Fillmore
FIR19-00485 INSP-Final Inspection8/27/20198/29/20198/29/2019 12:52:19 PMPPASS
Permit finaled.
FIR19-00374 INSP-Sprinkler Rough-in8/29/20198/29/20198/29/2019 12:30:09 PMPPART
Tenting on the third floor needs repaired. I noted two pendant heads that are overspaced on the third floor. First floor FDC piping has not been installed yet. No piping to be covered.
NAF19-00014 INSP-Sprinkler Rough-in/Hydro8/28/20198/29/20198/29/2019 11:36:48 AMACANC
Wrong inspection type scheduled. Should have been a fire life safety final. Call prior to going Phone #: 2087132042 >> Inspection requested via mobile web by Ryan
NAF19-00014 INSP-Final8/29/20198/29/20198/29/2019 11:32:35 AMPDONE
Life safety passed. The building inspector is approving the sub tenant exiting path that is not addressed on these plans as per the owner and our discussion.
NAF18-00126 INSP-Final8/28/20198/29/20198/29/2019 11:16:06 AMAPART
A temporary for life safety is approved by Boise Fire, for 30 days, until the shell/core BLD and the project related fire sprinkler permit, for the center area is addressed. Call prior to going Phone #: 2088304606 >> Inspection requested via mobile web by Zack
FIR18-00525 INSP-Final Inspection8/28/20198/29/20198/29/2019 10:04:24 AMAFAIL
Not ready for a final yet. Inspection was actually a walk through for the completed areas. The work in the finished areas has been completed. I noted one missing sprinkler canopy. Need rough to coover for the remaining west end first floor. Jon Beazer is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
BLD18-03122 BLD-Other8/28/20198/29/20198/29/2019 10:01:32 AMAFAIL
Wrong inspection number scheduled. Should be a FIR. Tenting is not approved. tenting // Pat Phone #: ###-####
BLD19-01979 FIRE-Final Inspection8/28/20198/29/20198/29/2019 8:18:52 AMAPASS
Life safety passed. SIgned card. Scott Phone #: ###-####