Inspections for the day of: Tuesday, September 10, 2019.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR19-00478 INSP-Final Inspection9/9/20199/10/20199/11/2019 7:02:09 AMPPASS
Permit finaled.

All of the bent piping appears to meet NFPA 13 6.3.8. Contact: Steven Vaughn Phone #: ###-#### Inspection requested via web by Hunter Fillmore
FIR19-00637 INSP-Final Inspection9/9/20199/10/20199/10/2019 4:13:31 PMPPASS
Permit finaled. Lee performed the inspection.

Call prior to going Phone #: 2086810381 >> Inspection requested via mobile web by Doug Lessa
FIR19-00626 INSP-Final Inspection9/10/20199/10/20199/10/2019 4:09:26 PMPPASS
permit finaled.

Zack Phone #: ###-####
FIR19-00653 INSP-Final Inspection9/10/20199/10/20199/10/2019 4:08:55 PMPPASS
permit finaled. Zack Phone #: ###-####
FIR18-00789 INSP-Final Inspection9/6/20199/10/20199/10/2019 1:22:25 PMPFAIL
Project is not ready for final yet. Todays inspection was to witness the fire pump certification. Final on shell and pump run with capital pump Phone #: ###-#### Inspection requested via web by Sam Ball
FIR19-00372 INSP-Final Inspection9/9/20199/10/20199/10/2019 10:58:53 AMPCANC
Call James before heading out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
FIR19-00290 INSP-Sprinkler Rough-in9/10/20199/10/20199/10/2019 10:34:30 AMPPASS
See the city approved plans for piping above the hardlids on first and second floors where piping is ok to cover.
Todd Ketterling is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
FIR19-00374 INSP-Sprinkler Rough-in9/9/20199/10/20199/10/2019 9:06:24 AMAPASS
This is a duplicate inspection for approval to cover the two east most third floor apartments.

Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
FIR19-00662 INSP-Sprinkler Rough-in9/10/20199/10/20199/10/2019 9:05:09 AMPPASS
The underground supply piping is ok to cover from the point of connection to the last 45 fitting. The IBR, when installed, will need cover inspection.

Jon Beazer is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
FIR19-00478 INSP-Sprinkler Rough-in9/9/20199/10/20199/10/2019 8:46:47 AMAPART
The deflector distance from the ceiling has been corrected but the hydro test failed due to visible leakage. Contact: Steven Vaughn Phone #: ###-#### Inspection requested via web by Hunter Fillmore
FIR19-00221 INSP-Sprinkler Rough-in9/9/20199/10/20199/10/2019 8:45:25 AMAPASS
See the city approved plans for first floor piping locations that are ok for cover. Tom Phone #: ###-####