Inspections for the day of: Friday, September 27, 2019.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR18-00892 INSP-Sprinkler Rough-in9/26/20199/27/20199/27/2019 2:46:10 PMPPART
Tenting failed for all areas. No piping to be covered. Rough-in passed for the single level area of work but again no piping can be covered. Also prior to a final inspection R38 insulation value will need to be provided.

Phone #: ###-#### Inspection requested via web by Connie Danes
FIR19-00678 INSP-Sprinkler Rough-in/Hydro9/27/20199/27/20199/27/2019 2:43:38 PMPPART
Main water supply hydro test witnessed with no pressure loss. The three cpvc supplies all failed due to visible loss at the guages.

Call James, might be ready this morning if you can go out earlier. Thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
FIR18-00957 INSP-Sprinkler Rough-in/Hydro9/26/20199/27/20199/27/2019 11:22:53 AMAPASS
24 hour air test witnessed for the dry pipe system. // Ruddy Phone #: ###-####
FIR19-00606 INSP-Final Inspection9/27/20199/27/20199/27/2019 9:44:34 AMPPART
Work in phase 1 is complete. POC is Karl with Orchard Partners Phone #: ###-#### Inspection requested via web by Chris Green
FIR19-00699 INSP-Final Inspection9/27/20199/27/20199/27/2019 9:43:20 AMPPART
Work in phase 1 area complete. Phone #: ###-#### Inspection requested via web by John Siewert
BLD19-01838 FIRE-Final Inspection9/26/20199/27/20199/27/2019 9:29:48 AMAPART
Life safety passed in the Phase 1 area of work. Carl Phone #: ###-####
FIR19-00697 INSP-Final Inspection9/26/20199/27/20199/27/2019 9:10:34 AMAPASS
Permit finaled. Phone #: ###-#### Inspection requested via web by Jonathan LaFond