Inspections for the day of: Tuesday, January 15, 2019.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMike Jordan
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD18-02321 BLD-Framing/Rough-in1/15/20191/15/20191/15/2019 3:21:57 PMPPASS
Phone #: ###-#### Inspection requested via web by Joel Hirtle
BLD17-02871 BLD-Energy code compliance1/15/20191/15/20191/15/2019 2:48:47 PMPPART
John Phone #: ###-####. A correction notice was issued to have architect recalculate the comm check using the R30 value at the vaulted roof areas in lieu of the R38.
BLD18-02774 BLD-Framing/Rough-in1/15/20191/15/20191/15/2019 1:09:41 PMPPASS
Trent Phone #: ###-####
BLD19-00146 BLD-Framing/Rough-in1/15/20191/15/20191/15/2019 12:53:25 PMPPASS
Ryan Phone #: ###-####
BLD18-02176 BLD-Footing1/14/20191/15/20191/15/2019 10:55:15 AMAPART
we would like an early A M inspection on rebar for an after noon pore thanks Phone #: ###-#### Inspection requested via web by Steve Mitchell. Column pad footings for canopy. Per contractor, will be tented and heated, forms will be pre heated with a weed burner. Special inspector on site.
BLD18-03981 BLD-Footing1/10/20191/15/20191/15/2019 10:16:03 AMAPASS
Phone #: ###-#### Inspection requested via web by Laurie Hoelscher
BLD17-04568 BLD-Ceiling Grid Inspection1/14/20191/15/20191/15/2019 9:47:22 AMAPASS
Bob Phone #: ###-####
BLD18-02793 BLD-Final1/14/20191/15/20191/15/2019 9:12:02 AMAPASS
Brayden Phone #: ###-####. Ok for perm occ. Per contractor no mech. work was done. Noted to contracotr that he will need to get that item removed.
BLD18-04426 BLD-Final1/14/20191/15/20191/15/2019 8:30:36 AMANR
call if you have any questions- Domrick Phone #: ###-####. Needs electrical final.