BLD19-00726
| BLD-Final | 1/21/2020 | 1/22/2020 | 1/22/2020 4:50:36 PM | P | PEND |
|
|
Tom Phone #: ###-####. Needs to provide panic hardware on egress doors from mech/elec room. Outstanding plumbing permit as well.
|
BLD18-04369
| BLD-Framing/Rough-in | 1/22/2020 | 1/22/2020 | 1/22/2020 3:13:00 PM | P | PASS |
|
|
First floor rough framing for cover Phone #: ###-#### Inspection requested via web by Jared Waggoner. 1st. floor i nterior steel stud framed walls ok. hardlids ok pending mech. rough in inspection.
|
BLD18-04243
| BLD-Framing/Rough-in | 1/22/2020 | 1/22/2020 | 1/22/2020 3:11:40 PM | P | PASS |
|
|
First floor rough framing for cover Phone #: ###-#### Inspection requested via web by Jared Waggoner. 1st floor interior steel stud walls ok. Hardlids ok pending mech. rough in inspection.
|
BLD18-04521
| BLD-Framing/Rough-in | 1/22/2020 | 1/22/2020 | 1/22/2020 2:42:52 PM | P | PASS |
|
|
Building 12 - 1st Floor Energy Seal, Fire Caulking ; Framing Building 12 - 2nd Floor Ceilings 1st layer gyp and 2nd layer gyp overlap Phone #: ###-#### Inspection requested via web by Bob Goodwin
|
BLD19-04372
| BLD-Framing/Rough-in | 1/22/2020 | 1/22/2020 | 1/22/2020 1:41:38 PM | P | PASS |
|
|
|
BLD19-04256
| BLD-Energy code compliance | 1/21/2020 | 1/22/2020 | 1/22/2020 1:31:36 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD19-04256
| BLD-Framing/Rough-in | 1/21/2020 | 1/22/2020 | 1/22/2020 1:31:23 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD19-04372
| BLD-Framing/Rough-in | 1/21/2020 | 1/22/2020 | 1/22/2020 1:30:58 PM | P | CANC |
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD18-04294
| BLD-Ceiling Grid Inspection | 1/21/2020 | 1/22/2020 | 1/22/2020 10:57:05 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Roger Graves
|
BLD19-04257
| BLD-Framing/Rough-in | 1/21/2020 | 1/22/2020 | 1/22/2020 10:16:27 AM | A | NR |
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Needs plumbing rough in inspection.
|
BLD19-00726
| BLD-Conference | 1/21/2020 | 1/22/2020 | 1/22/2020 10:15:32 AM | A | DONE |
|
|
Tom Phone #: ###-####. Noted issues with approved city plans on site, they do not appear to be the most current set with addtional redlines on sheets A1.0 and A6.0. Noted door hardware issues from mech room area for egress. Egress doors to have panic hardware. Doors from the mech. room to the wash tunnel need to have the sticker placed stating these doors to remain unlocked while building is occupied.
|
BLD20-00064
| BLD-Footing | 1/21/2020 | 1/22/2020 | 1/22/2020 8:42:29 AM | A | PART |
|
|
Mike Phone #: ###-####. Setbacks ok. A seperate electrical permit is required and inspection for grounding on pool is required prior to cover.
|