BLD17-00543
| DOC - Permit Finaled | 1/31/2018 | 1/31/2018 | 1/31/2018 5:06:04 PM | P | PASS |
|
|
Work has been done and completed and C.O issued.
|
MIS17-00248
| MIS-Aging Inspection | 1/31/2018 | 1/31/2018 | 1/31/2018 5:04:33 PM | | PEND |
|
|
|
MIS17-00399
| BLD-Conference | 12/27/2017 | 1/31/2018 | 1/31/2018 5:04:14 PM | A | DONE |
|
|
Check on progress. 25 day notice due. Issuued a correction notice to have homeowner contact me to give a status update. No plans or engineering have been submited as of yet. Today is end of 25 day notice. Homeowner has had 40 business days since initial correction notice. Home owner did call me back and stated that he has potentially found an engineer to help him but will not arrive at his home until end of 2nd week in Feb. Homeowner to call after his meeting with engineer to give staus update. Another inspection has bee scheduled for feb. 19th.
|
BLD17-03778
| BLD-Final | 1/30/2018 | 1/31/2018 | 1/31/2018 4:38:56 PM | P | NR |
|
|
Egor Phone #: ###-####
|
BLD17-02960
| BLD-Final | 1/30/2018 | 1/31/2018 | 1/31/2018 4:38:16 PM | P | NR |
|
|
Egor Phone #: ###-####
|
BLD17-01305
| BLD-Final | 1/30/2018 | 1/31/2018 | 1/31/2018 4:37:57 PM | P | NR |
|
|
Egor Phone #: ###-####
|
BLD17-01449
| BLD-Final | 1/30/2018 | 1/31/2018 | 1/31/2018 4:37:12 PM | P | NR |
|
|
Egor Phone #: ###-####
|
BLD17-04297
| BLD-Framing/Rough-in | 1/31/2018 | 1/31/2018 | 1/31/2018 4:36:32 PM | P | PASS |
|
|
Egor-Partial framing Phone #: ###-####. Exterior steel stud framed walls and for canopys and columns for new facade on space A and B.
|
BLD17-03247
| BLD-Final | 1/30/2018 | 1/31/2018 | 1/31/2018 4:35:33 PM | P | FAIL |
|
|
Egor Phone #: ###-####. Vertical grab abrs in restrooms mounted to far from rear wall. Mount ADA restromm signs on wall. Provide exterior landing at man door. Post occupant load sing in meeting room. Install aditional handrail on new stairs. Sheetrock under new stairs. Pedestrian protection Overhead, required at main entry and man door while new facade work is taking place.
|
BLD17-02416
| BLD-Wall Bracing | 1/31/2018 | 1/31/2018 | 1/31/2018 2:13:50 PM | P | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by Marty Short
|
BLD17-02411
| BLD-Wall Bracing | 1/31/2018 | 1/31/2018 | 1/31/2018 2:13:39 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Marty Short
|
BLD17-04667
| BLD-Final | 1/30/2018 | 1/31/2018 | 1/31/2018 2:12:52 PM | P | PART |
|
|
Kelly-please call 30 minutes prior to meet Phone #: ###-####. ok for temp occ.
|
BLD18-00256
| BLD-Final | 1/30/2018 | 1/31/2018 | 1/31/2018 1:12:49 PM | P | PART |
|
|
Philip Phone #: ###-####. Ok for temp occ. Needs racking permit.
|
BLD16-04309
| BLD-Final | 1/31/2018 | 1/31/2018 | 1/31/2018 1:08:11 PM | P | PASS |
|
|
Please accommodate a 1 o''clock inspection. Phone #: ###-#### Inspection requested via web by David Scaggs. OK for temp. occ. Will be ok for perm occ once zoning and public works signs perm.
|
BLD17-01088
| BLD-Framing/Rough-in | 1/30/2018 | 1/31/2018 | 1/31/2018 12:00:06 PM | A | PASS |
|
|
Charles Phone #: ###-####. interior steel stud framed walls at rooms 117,118,119, 146 and 147. Furred walls on passage 115.
|
BLD16-04309
| BLD-Final | 1/31/2018 | 1/31/2018 | 1/31/2018 10:11:23 AM | P | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by David Scaggs Inspection cancelled from web by: David Scaggs
|
BLD17-04532
| BLD-Ceiling Grid Inspection | 1/30/2018 | 1/31/2018 | 1/31/2018 10:03:14 AM | A | PASS |
|
|
Call half hour before to meet // Tim Phone #: ###-####
|
BLD17-03692
| BLD-Wall Bracing | 1/29/2018 | 1/31/2018 | 1/31/2018 9:50:07 AM | A | FAIL |
|
|
Framer is on site. Phone #: ###-#### Inspection requested via web by Chris Laraway. Install all mising hold downs on first floor, install missing floor to floor strap on 2nd. floor. Provide portal frame in back or engineering. Provide the wall bracing on garage wall. Correction notice issued. ok to tyvek.
|
BLD17-02166
| BLD-Final | 1/30/2018 | 1/31/2018 | 1/31/2018 9:02:20 AM | P | PASS |
|
|
Mike GC Phone #: ###-####
|
BLD17-02166
| DOC - Permit Finaled | 1/31/2018 | 1/31/2018 | 1/31/2018 9:02:05 AM | P | PASS |
|
|
|
BLD17-03963
| BLD-Framing/Rough-in | 1/29/2018 | 1/31/2018 | 1/31/2018 8:46:02 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Philip Yates. Ok to insulate.
|
BLD17-00013
| BLD-Final | 1/30/2018 | 1/31/2018 | 1/31/2018 8:11:50 AM | P | CANC |
|
|
Rick Phone #: ###-####. Cancelled by Rick via phone call.
|
BLD18-00256
| BLD-Final | 1/30/2018 | 1/31/2018 | 1/31/2018 12:00:00 AM | A | CANC |
|
|
call when on way // Philip Phone #: ###-####
|