Inspections for the day of: Thursday, November 21, 2019.
Number of inspections: 21
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMike Jordan
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD19-04525 BLD-Final11/21/201911/21/201911/21/2019 3:34:06 PMPDONE
Larry Phone #: ###-####
BLD19-04525 DOC - Permit Finaled11/21/201911/21/201911/21/2019 3:33:57 PMPPASS
All work appeared to be done in accordance with local codes and ordinances.
BLD19-02014 BLD-Wall Bracing11/20/201911/21/201911/21/2019 3:33:24 PMPNR
Phone #: ###-#### Inspection requested via web by Joel Hirtle
BLD19-02648 BLD-Other11/21/201911/21/201911/21/2019 2:25:11 PMPDONE
Confirm applicant has vacated space - now occupying unit 104 Phone #: ###-####
BLD19-02648 DOC - Permit Finaled11/21/201911/21/201911/21/2019 2:25:04 PMPPASS
Tenant has vacated the space.
BLD19-03278 BLD-Conference11/21/201911/21/201911/21/2019 2:24:43 PMPDONE
verify tenant has vacated the building to FNL permit Phone #: ###-####
BLD19-03278 DOC - Permit Finaled11/21/201911/21/201911/21/2019 2:24:35 PMPPASS
Tenant has vacated the space.
BLD19-03384 BLD-Wall Bracing11/21/201911/21/201911/21/2019 2:24:09 PMPPASS
Jeff Phone #: ###-####
BLD19-04368 BLD-Final11/21/201911/21/201911/21/2019 1:36:17 PMPPASS
BLD19-04368 DOC - Permit Finaled11/21/201911/21/201911/21/2019 1:36:07 PMPPASS
BLD19-04368 BLD-Footing11/20/201911/21/201911/21/2019 1:35:57 PMPPASS
An early PM inspection for this would be the best if possible. Alex will be doing the installation and his cell number is ###-####. Thanks. Phone #: ###-#### Inspection requested via web by rich prasch
BLD19-03364 BLD-Foundation11/21/201911/21/201911/21/2019 1:16:10 PMPCANC
pour at 1:30 // SAm Phone #: ###-####
BLD19-03364 BLD-Footing11/21/201911/21/201911/21/2019 1:16:03 PMPPASS
pour at 1:30 // SAm Phone #: ###-####
BLD19-04172 BLD-Foundation11/20/201911/21/201911/21/2019 1:07:46 PMPPASS
Dane- foundation wall Phone #: ###-####
BLD19-04169 BLD-Foundation11/20/201911/21/201911/21/2019 11:59:39 AMAPASS
Dane- foundation wall Phone #: ###-####
BLD19-04173 BLD-Foundation11/20/201911/21/201911/21/2019 11:59:22 AMAPASS
Dane- foundation wall Phone #: ###-####
BLD19-02012 BLD-Framing/Rough-in11/20/201911/21/201911/21/2019 11:36:50 AMAFAIL
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Trusses not fully seated in hangars in garage at 2 ply girder. ok to insulate.
BLD19-00733 BLD-Energy code compliance11/20/201911/21/201911/21/2019 11:02:11 AMAPASS
not ready until 10 am // Kevin Phone #: ###-####
BLD19-04327 BLD-Wall cover11/20/201911/21/201911/21/2019 9:50:23 AMAPART
text for lock box code // Ethan Phone #: ###-####. No new framing or electrical work. will pull plumbing and mecg. permits for new duct work amd fixtures. Needs to complete aireseal prior to insulation and call for inspection.
BLD19-01556 BLD-Final11/20/201911/21/201911/21/2019 9:13:45 AMAPEND
Barney Phone #: ###-####. Need final letter from special inspection agency and zoning final.
BLD19-03364 BLD-Footing11/20/201911/21/201911/21/2019 8:47:47 AMAFAIL
Sam Phone #: ###-####. Column pad footings not the min. 10 inches deep per the approved plans. Also noted that ground, rebar and form work below the min. 34 degress required for concrete placement.