Inspections for the day of: Thursday, December 19, 2019.
Number of inspections: 25
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMike Jordan
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MIS18-00414 MIS-Aging Inspection12/19/201912/19/201912/20/2019 3:21:05 PM DEFR
BLD18-02830 BLD-Aging Inspection12/19/201912/19/201912/20/2019 3:19:56 PM CANC
MIS18-00409 MIS-Aging Inspection12/19/201912/19/201912/20/2019 3:19:16 PM PASS
BLD18-02846 BLD-Aging Inspection12/19/201912/19/201912/20/2019 3:18:09 PM CANC
MIS19-00008 MIS-Aging Inspection12/19/201912/19/201912/20/2019 3:17:05 PM DONE
BLD18-03576 BLD-Final12/19/201912/19/201912/19/2019 5:13:42 PMPPASS
Call for access Phone #: 2089916570 >> Inspection requested via mobile web by Ben Wolf
BLD18-03576 DOC - Permit Finaled12/19/201912/19/201912/19/2019 5:13:31 PMPPASS
BLD19-04853 BLD-Framing/Rough-in12/18/201912/19/201912/19/2019 4:32:10 PMPPASS
Ryan Phone #: ###-####
BLD19-00561 BLD-Footing12/18/201912/19/201912/19/2019 4:18:21 PMPPASS
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constru
BLD18-04521 BLD-Framing/Rough-in12/19/201912/19/201912/19/2019 4:18:21 PMPPART
Framing inspection in pre-rock areas. Phone #: ###-#### Inspection requested via web by Kris Linnell. Pre rock and fire caulking. work in progress.
BLD19-03316 BLD-Footing12/19/201912/19/201912/19/2019 2:51:41 PMPPASS
can they ring before they come Phone #: ###-#### Inspection requested via web by Glen Farrell
BLD19-04551 BLD-Final12/16/201912/19/201912/19/2019 2:51:00 PMPPASS
call for access- Shelly Phone #: ###-####. Ok for perm occ.
BLD19-04623 BLD-Framing/Rough-in12/19/201912/19/201912/19/2019 2:30:39 PMPFAIL
Phone #: ###-#### Inspection requested via web by Travis Knutson. Needs to remove screws from top plate to grid and install supports to structure above.
BLD19-03384 BLD-Framing/Rough-in12/19/201912/19/201912/19/2019 1:58:11 PMPFAIL
Jeff Phone #: ###-####. Complete lateral bracing on A03,A04,A05 and A06 trusses. Fireblock concealed space by shower/tub at ceiling. Provide strongbacks on both gable ends. provide 2x6 studs under top plate breaks in garage, both sides, (east and west)
BLD19-04292 BLD-Final12/16/201912/19/201912/19/2019 1:33:54 PMPPASS
Mirins Phone #: ###-####
BLD19-04292 DOC - Permit Finaled12/19/201912/19/201912/19/2019 1:33:47 PMPPASS
BLD19-04249 BLD-Framing/Rough-in12/18/201912/19/201912/19/2019 1:11:16 PMPPASS
Jeff Phone #: ###-####. New beam in kitchen.
BLD19-04667 BLD-Framing/Rough-in12/18/201912/19/201912/19/2019 12:35:39 PMADONE
Please call Brian Prussia with any questions or concerns at ###-#### Phone #: ###-#### Inspection requested via web by BRS Permitting. No work needed to upgrade existing roof.
BLD19-04180 BLD-Energy code compliance12/18/201912/19/201912/19/2019 9:54:59 AMANR
Phone #: ###-#### Inspection requested via web by Joel Hirtle
BLD19-04307 BLD-Footing12/18/201912/19/201912/19/2019 9:09:52 AMAPASS
Dean Phone #: ###-####
BLD19-03756 BLD-Energy code compliance12/18/201912/19/201912/19/2019 8:58:14 AMANR
Gari Phone #: ###-####
BLD19-03756 BLD-Framing/Rough-in12/18/201912/19/201912/19/2019 8:58:01 AMAFAIL
Gari Phone #: ###-####. Sheeting needs to be installed to follow portal frame method.
BLD19-02642 BLD-Final12/18/201912/19/201912/19/2019 8:36:35 AMAPASS
Greg Phone #: ###-####
BLD19-02642 DOC - Permit Finaled12/19/201912/19/201912/19/2019 8:36:26 AMPPASS
BLD19-04346 BLD-Final12/18/201912/19/201912/18/2019 12:43:29 PMAPASS
Melinda- call for access Phone #: ###-####. Ok for perm occ.