BLD17-00268
| BLD-Framing/Rough-in | 12/5/2017 | 12/5/2017 | 12/5/2017 3:40:54 PM | P | PASS |
|
|
Cory Phone #: ###-####. Steel stud framing for 3hr. wall at bldg. #3.
|
BLD16-02806
| BLD-Other | 12/5/2017 | 12/5/2017 | 12/5/2017 3:05:48 PM | P | PASS |
|
|
Roof cover inspection Phone #: ###-#### Inspection requested via web by Ryan Wilhelm. Ok to cover roof.
|
BLD17-03433
| BLD-Other | 12/5/2017 | 12/5/2017 | 12/5/2017 1:54:24 PM | P | PASS |
|
|
block & tie // Ashley Phone #: ###-####. Block and Tie only ok.
|
BLD16-04506
| BLD-Footing | 12/5/2017 | 12/5/2017 | 12/5/2017 1:44:50 PM | P | PASS |
|
|
Rebar - Shane Phone #: ###-####. Interior thickend footings.
|
BLD16-04507
| BLD-Footing | 12/5/2017 | 12/5/2017 | 12/5/2017 1:44:31 PM | P | PASS |
|
|
Rebar - Shane Phone #: ###-####. Interior thickend footings.
|
BLD16-02749
| BLD-Footing | 12/5/2017 | 12/5/2017 | 12/5/2017 1:44:13 PM | P | PASS |
|
|
Rebar - Shane Phone #: ###-####. Interior thickend footings.
|
BLD16-04509
| BLD-Footing | 12/5/2017 | 12/5/2017 | 12/5/2017 1:43:57 PM | P | PASS |
|
|
Rebar - Shane Phone #: ###-####. Interior thickend footings.
|
BLD16-02746
| BLD-Footing | 12/5/2017 | 12/5/2017 | 12/5/2017 1:43:42 PM | P | PASS |
|
|
Rebar - Shane Phone #: ###-####. Interior thickend footings.
|
BLD16-04501
| BLD-Footing | 12/5/2017 | 12/5/2017 | 12/5/2017 1:43:20 PM | P | PASS |
|
|
Rebar - Shane Phone #: ###-####. Interior thickend footings.
|
BLD16-04510
| BLD-Footing | 12/5/2017 | 12/5/2017 | 12/5/2017 1:43:02 PM | P | PASS |
|
|
Rebar - Shane Phone #: ###-####. Interior thickend footings.
|
BLD16-04502
| BLD-Footing | 12/5/2017 | 12/5/2017 | 12/5/2017 1:42:43 PM | P | PASS |
|
|
Rebar - Shane Phone #: ###-####. Interior thickend footings.
|
BLD16-02753
| BLD-Wall Bracing | 12/5/2017 | 12/5/2017 | 12/5/2017 1:42:11 PM | P | FAIL |
|
|
Shane Phone #: ###-####
|
BLD16-02752
| BLD-Wall Bracing | 12/5/2017 | 12/5/2017 | 12/5/2017 1:41:57 PM | P | FAIL |
|
|
Shane Phone #: ###-####
|
BLD17-03930
| BLD-Framing/Rough-in | 12/4/2017 | 12/5/2017 | 12/5/2017 1:04:12 PM | A | PASS |
|
|
Eric Phone #: ###-####
|
BLD17-04137
| BLD-Footing | 12/4/2017 | 12/5/2017 | 12/5/2017 11:38:48 AM | A | PART |
|
|
Mike Phone #: ###-####
|
BLD17-00058
| BLD-Framing/Rough-in | 12/1/2017 | 12/5/2017 | 12/5/2017 11:19:37 AM | A | CANC |
|
|
Roger Phone #: ###-####
|
BLD17-00058
| BLD-Wall Bracing | 12/5/2017 | 12/5/2017 | 12/5/2017 11:19:31 AM | A | PART |
|
|
Roger Phone #: ###-####. Exterior walls. South exterior wall below low roof not completed.
|
BLD17-02412
| BLD-Footing | 12/4/2017 | 12/5/2017 | 12/5/2017 8:44:00 AM | A | PASS |
|
|
Interior footings, Concrete scheduled for 10am Phone #: ###-#### Inspection requested via web by Marty Short
|
BLD17-02410
| BLD-Footing | 12/4/2017 | 12/5/2017 | 12/5/2017 8:43:49 AM | A | PASS |
|
|
Interior footings, Concrete scheduled for 10am Phone #: ###-#### Inspection requested via web by Marty Short
|
BLD17-02166
| BLD-Energy code compliance | 12/4/2017 | 12/5/2017 | 12/5/2017 8:43:21 AM | A | PASS |
|
|
Mike Phone #: ###-####
|