BLD17-03247
| BLD-Framing/Rough-in | 12/6/2017 | 12/6/2017 | 12/6/2017 6:51:53 PM | P | PART |
|
|
Igor Phone #: ###-####. No city approved plans on site. Ok to one side only. Will call in for reinspection tomorrow in the pm with approved set of city plans.
|
BLD17-03630
| BLD-Footing | 12/5/2017 | 12/6/2017 | 12/6/2017 6:50:54 PM | P | FAIL |
|
|
James Phone #: ###-####. Needs to provide city set of approved plans and small docs.
|
BLD17-00058
| BLD-Framing/Rough-in | 12/5/2017 | 12/6/2017 | 12/6/2017 3:46:32 PM | P | CANC |
|
|
Roger Phone #: ###-####
|
BLD17-00058
| BLD-Wall Bracing | 12/6/2017 | 12/6/2017 | 12/6/2017 3:46:26 PM | P | PASS |
|
|
Roger Phone #: ###-####. The south exteror wall below the low roof has been corrected.
|
BLD17-04164
| BLD-Final | 12/6/2017 | 12/6/2017 | 12/6/2017 3:11:49 PM | P | DONE |
|
|
Justin Hamby Phone #: ###-#### Inspection requested via web by Laurie Hoelscher
|
BLD17-04164
| DOC - Permit Finaled | 12/6/2017 | 12/6/2017 | 12/6/2017 3:11:42 PM | P | PASS |
|
|
|
BLD17-03645
| BLD-Wall cover | 12/5/2017 | 12/6/2017 | 12/6/2017 3:06:57 PM | P | CANC |
|
|
Inspection requested via web by Richard Evans
|
BLD17-03645
| BLD-Energy code compliance | 12/6/2017 | 12/6/2017 | 12/6/2017 3:06:50 PM | P | PASS |
|
|
Inspection requested via web by Richard Evans
|
BLD17-03639
| BLD-Wall cover | 12/5/2017 | 12/6/2017 | 12/6/2017 3:06:32 PM | P | CANC |
|
|
Inspection requested via web by Richard Evans
|
BLD17-03639
| BLD-Energy code compliance | 12/6/2017 | 12/6/2017 | 12/6/2017 3:06:26 PM | P | PASS |
|
|
Inspection requested via web by Richard Evans
|
BLD16-02806
| BLD-Framing/Rough-in | 12/6/2017 | 12/6/2017 | 12/6/2017 1:44:14 PM | P | PASS |
|
|
Shear wall inspection Phone #: ###-#### Inspection requested via web by Ryan Wilhelm. Exterior shear only ok.
|
BLD17-04137
| BLD-Foundation | 12/5/2017 | 12/6/2017 | 12/6/2017 1:07:47 PM | P | PART |
|
|
Mike Phone #: ###-####
|
BLD17-01088
| BLD-Ceiling Grid Inspection | 12/5/2017 | 12/6/2017 | 12/6/2017 11:28:50 AM | A | PASS |
|
|
Charles Phone #: ###-####. Ceiling grid at main corridor between b occupancy and 3hr. fire wall ok. Also did courtesey walk through on B occupancy portion of building.
|
BLD17-00651
| BLD-Framing/Rough-in | 12/5/2017 | 12/6/2017 | 12/6/2017 9:43:10 AM | A | NR |
|
|
request mid morning or afternoon // Jim Phone #: ###-####. Needs electrical rough in inspection and complete foam seal.
|
BLD17-03307
| BLD-Final | 12/5/2017 | 12/6/2017 | 12/6/2017 9:23:31 AM | A | DONE |
|
|
Shawn Phone #: ###-####
|
BLD17-03307
| DOC - Permit Finaled | 12/6/2017 | 12/6/2017 | 12/6/2017 9:22:57 AM | P | PASS |
|
|
All work appeared to be done in accordance with local codes and ordinances.
|
BLD17-00358
| BLD-Final | 12/5/2017 | 12/6/2017 | 12/6/2017 9:12:22 AM | A | FAIL |
|
|
Doyle Phone #: ###-####. Provide 20 min. door at garage to house and self closing. everything else ok.
|
BLD17-04330
| BLD-Final | 12/5/2017 | 12/6/2017 | 12/6/2017 8:50:21 AM | A | NR |
|
|
Gayle Phone #: ###-####. Shell and core final not called in. Still needs zoning and public works to final. Also will need to adress were the pour back strip not yet complete prior to occupancy.
|
BLD17-03455
| BLD-Energy code compliance | 12/5/2017 | 12/6/2017 | 12/6/2017 8:43:20 AM | A | PASS |
|
|
Tom Phone #: ###-####
|