BLD19-04199
| BLD-Final | 12/5/2019 | 12/6/2019 | 12/6/2019 4:00:59 PM | P | NR |
|
|
Please call our onsite contact, Ashley: ###-#### Phone #: ###-#### Inspection requested via web by BRS Permitting. Electrical final has failed.
|
BLD18-04294
| BLD-Energy code compliance | 12/6/2019 | 12/6/2019 | 12/6/2019 3:29:34 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Roger Graves. Remaining walls ok to cover.
|
BLD19-04707
| BLD-Final | 12/3/2019 | 12/6/2019 | 12/6/2019 3:28:47 PM | P | NR |
|
|
Hannan Phone #: ###-####. An electrical permit is required prior to final.
|
BLD19-03898
| BLD-Framing/Rough-in | 12/5/2019 | 12/6/2019 | 12/6/2019 3:00:41 PM | P | PASS |
|
|
Partial inspection for West side of building. Phone #: ###-#### Inspection requested via web by Nate Carriveau. Interior steel stud framed walls, west half only. No grid, hardlids or soffits at this time.
|
BLD19-04144
| BLD-Final | 12/5/2019 | 12/6/2019 | 12/6/2019 2:15:05 PM | P | PASS |
|
|
Douglass Phone #: ###-####
|
BLD19-04144
| DOC - Permit Finaled | 12/6/2019 | 12/6/2019 | 12/6/2019 2:14:56 PM | P | PASS |
|
|
|
BLD19-04254
| BLD-Foundation | 12/5/2019 | 12/6/2019 | 12/6/2019 1:45:41 PM | P | PART |
|
|
Dane Phone #: ###-####
|
BLD19-04255
| BLD-Footing | 12/5/2019 | 12/6/2019 | 12/6/2019 1:45:30 PM | P | PART |
|
|
Dane Phone #: ###-####
|
BLD19-04258
| BLD-Footing | 12/5/2019 | 12/6/2019 | 12/6/2019 1:45:14 PM | P | PART |
|
|
Dane Phone #: ###-####
|
BLD19-01513
| BLD-Wall cover | 12/5/2019 | 12/6/2019 | 12/6/2019 1:18:05 PM | P | PASS |
|
|
Fire Sprinkler to re-inspect in the am. for Cover approval. Thank you. Phone #: ###-#### Inspection requested via web by Chris Laraway
|
BLD19-01513
| BLD-Energy code compliance | 12/6/2019 | 12/6/2019 | 12/6/2019 1:17:51 PM | P | PASS |
|
|
Fire Sprinkler to re-inspect in the am. for Cover approval. Thank you. Phone #: ###-#### Inspection requested via web by Chris Laraway
|
BLD19-01513
| BLD-Framing/Rough-in | 12/6/2019 | 12/6/2019 | 12/6/2019 1:17:38 PM | P | PASS |
|
|
Fire Sprinkler to re-inspect in the am. for Cover approval. Thank you. Phone #: ###-#### Inspection requested via web by Chris Laraway
|
BLD18-02176
| BLD-Final | 12/5/2019 | 12/6/2019 | 12/6/2019 11:20:56 AM | A | DONE |
|
|
Nacho Phone #: ###-####
|
BLD19-03317
| BLD-Final | 12/5/2019 | 12/6/2019 | 12/6/2019 9:27:30 AM | A | PASS |
|
|
Duan Phone #: ###-####. OK for temp occ. Will be ok for perm occ once mech. signs perm.
|
BLD19-00559
| BLD-Foundation | 12/5/2019 | 12/6/2019 | 12/6/2019 9:06:35 AM | A | PASS |
|
|
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constru
|
BLD19-00558
| BLD-Foundation | 12/5/2019 | 12/6/2019 | 12/6/2019 9:06:04 AM | A | PASS |
|
|
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constru
|
BLD19-04327
| BLD-Wall cover | 12/5/2019 | 12/6/2019 | 12/6/2019 8:53:58 AM | A | FAIL |
|
|
please text to get location of house Phone #: ###-#### Inspection requested via web by Ethan Gylling. Foam all missed penetrations. Obtain a plumbing permit and get rough in inspection on new plumbing. Correction notice posted. Do not cover.
|
BLD19-04292
| BLD-Framing/Rough-in | 12/5/2019 | 12/6/2019 | 12/6/2019 8:31:58 AM | A | DONE |
|
|
Please call Brian Prussia with any questions or concerns Phone #: ###-#### Inspection requested via web by BRS Permitting
|
BLD19-01513
| BLD-Wall cover | 12/5/2019 | 12/6/2019 | 12/5/2019 2:18:08 PM | A | CANC |
|
|
Sprinkler tenting inspection Thurs Afternoon. Cancel this inspection if Fire does not pass in the system. Please call Brad if there are any questions or other issues to be addressed. Thank you.. Phone #: ###-#### >> Inspection requested via web by Chris Laraway Inspection cancelled from web by: Chris Laraway
|
BLD19-04199
| BLD-Final | 12/5/2019 | 12/6/2019 | 12/5/2019 9:06:18 AM | P | CANC |
|
|
Please call our onsite contact, Ashley: ###-#### before arrival. Phone #: ###-#### >> Inspection requested via web by BRS Permitting Inspection cancelled from web by: BRS Permitting
|