Inspections for the day of: Tuesday, February 19, 2019.
Number of inspections: 14
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMike Jordan
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD18-02865 BLD-Final2/19/20192/19/20192/19/2019 4:22:41 PMPNR
call for access- Tim Phone #: ###-####. Needs mech. final.
BLD18-04569 BLD-Final2/15/20192/19/20192/19/2019 4:22:01 PMPNR
Randy Phone #: ###-####. Needs fire/life/safety final first.
BLD18-04462 BLD-Footing2/19/20192/19/20192/19/2019 3:19:09 PMPNR
Matt Phone #: ###-####
BLD19-00198 BLD-Footing2/19/20192/19/20192/19/2019 2:52:49 PMPPASS
Matt Phone #: ###-####
BLD19-00197 BLD-Footing2/19/20192/19/20192/19/2019 2:52:34 PMPPASS
Matt Phone #: ###-####
BLD18-03200 BLD-Foundation2/19/20192/19/20192/19/2019 2:16:31 PMPPART
Rebar // Jean Phone #: ###-####
BLD18-04399 BLD-Wall Bracing2/19/20192/19/20192/19/2019 1:57:58 PMPNR
Gaudy Phone #: ###-####
BLD18-04384 BLD-Wall Bracing2/19/20192/19/20192/19/2019 1:48:04 PMPPASS
BLD19-00047 BLD-Footing2/19/20192/19/20192/19/2019 1:26:50 PMPPART
Sergio Phone #: ###-####
BLD18-02176 BLD-Footing2/18/20192/19/20192/19/2019 12:43:39 PMAPART
early am Phone #: ###-#### Inspection requested via web by Steve Mitchell. Interior column pad footings on grid line 3, work in progress.
BLD19-00199 BLD-Wall Bracing2/18/20192/19/20192/19/2019 10:13:39 AMAPASS
Phone #: ###-#### Inspection requested via web by Joel Hirtle
BLD18-04578 BLD-Wall Bracing2/18/20192/19/20192/19/2019 9:55:52 AMAPASS
Phone #: ###-#### Inspection requested via web by Joel Hirtle
BLD18-04384 BLD-Wall Bracing2/18/20192/19/20192/19/2019 9:24:12 AMANR
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Rescheduled for this afternoon.
BLD17-03692 BLD-Final2/18/20192/19/20192/19/2019 9:15:54 AMAFAIL
Garage Code 4646. Thank you, Phone #: ###-#### Inspection requested via web by Chris Laraway. Glazing at mid landing of stairs is required to be tempered. Provide the blower door test results and post or the 3rd party airseal report. Correction notice posted.