MIS17-00042
| BLD-Conference | 2/21/2017 | 2/22/2017 | 2/22/2017 4:08:54 PM | P | DONE |
|
|
See notes on previous inspection. two seperate permits are being issued. one has been issued, the other is under review.
|
BLD16-02176
| BLD-Framing/Rough-in | 2/21/2017 | 2/22/2017 | 2/22/2017 3:34:59 PM | P | PASS |
|
|
Tim Phone #: ###-####. Interior steel stud walls for offices and restrooms, west half. ok to one side east half at roof access ladder.
|
BLD16-02420
| BLD-Footing | 2/21/2017 | 2/22/2017 | 2/22/2017 2:50:18 PM | P | NR |
|
|
Dane Phone #: ###-####. Will reschedule.
|
BLD16-03892
| BLD-Framing/Rough-in | 2/22/2017 | 2/22/2017 | 2/22/2017 2:40:57 PM | P | CANC |
|
|
Ken Phone #: ###-####
|
BLD16-04482
| BLD-Footing | 2/22/2017 | 2/22/2017 | 2/22/2017 1:50:35 PM | P | PASS |
|
|
|
BLD16-04482
| BLD-Footing | 2/21/2017 | 2/22/2017 | 2/22/2017 1:50:15 PM | A | PASS |
|
|
Butch-late AM if possible-pour time 2:00 Phone #: ###-####
|
BLD16-04163
| BLD-Foundation | 2/22/2017 | 2/22/2017 | 2/22/2017 1:30:26 PM | P | PASS |
|
|
|
BLD16-03397
| BLD-Wall Bracing | 2/22/2017 | 2/22/2017 | 2/22/2017 1:18:05 PM | P | PASS |
|
|
|
BLD17-00186
| BLD-Footing | 2/21/2017 | 2/22/2017 | 2/22/2017 11:17:19 AM | A | PASS |
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD16-04163
| BLD-Foundation | 2/21/2017 | 2/22/2017 | 2/22/2017 11:05:19 AM | A | NR |
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron. Moved to pm.
|
BLD17-00262
| BLD-Final | 2/21/2017 | 2/22/2017 | 2/22/2017 10:54:59 AM | A | PASS |
|
|
Scott Phone #: ###-####
|
BLD16-03040
| BLD-Energy code compliance | 2/17/2017 | 2/22/2017 | 2/22/2017 10:23:04 AM | A | PASS |
|
|
Blown in Blanket insulation Phone #: ###-#### Inspection requested via web by Joe Perdew
|
BLD16-03822
| BLD-Energy code compliance | 2/21/2017 | 2/22/2017 | 2/22/2017 10:16:45 AM | A | PASS |
|
|
Chris Phone #: ###-####
|
BLD16-03352
| BLD-Conference | 2/22/2017 | 2/22/2017 | 2/22/2017 10:04:21 AM | A | DONE |
|
|
Phone #: ###-#### Inspection requested via web by Shane Syndergaard
|
BLD16-01060
| BLD-Framing/Rough-in | 2/21/2017 | 2/22/2017 | 2/22/2017 9:37:42 AM | A | CANC |
|
|
Walls at bathtubs to insulate and pre-rock Phone #: ###-#### Inspection requested via web by Michael West. Moved to pm.
|
BLD16-04581
| BLD-Wall Bracing | 2/21/2017 | 2/22/2017 | 2/22/2017 9:30:57 AM | A | FAIL |
|
|
Bill Phone #: ###-####. Needs to install all missing blocking and nail. Install missing holdowns and straps.
|
BLD16-02985
| BLD-Energy code compliance | 2/17/2017 | 2/22/2017 | 2/22/2017 9:10:57 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD16-02985
| BLD-Framing/Rough-in | 2/22/2017 | 2/22/2017 | 2/22/2017 9:10:39 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD16-03397
| BLD-Wall Bracing | 2/21/2017 | 2/22/2017 | 2/22/2017 8:41:03 AM | A | FAIL |
|
|
Shear // Brett Phone #: ###-####. fasten per the engineering.
|
BLD16-03129
| BLD-Wall Bracing | 2/21/2017 | 2/22/2017 | 2/22/2017 8:21:15 AM | A | PASS |
|
|
|