BLD18-04531
| BLD-Conference | 2/28/2019 | 2/28/2019 | 2/28/2019 3:51:09 PM | P | DONE |
|
|
Tom Phone #: ###-####
|
BLD19-00003
| BLD-Final | 2/26/2019 | 2/28/2019 | 2/28/2019 3:44:48 PM | P | DONE |
|
|
Phone #: ###-#### Inspection requested via web by Brecklee Brown
|
BLD19-00003
| DOC - Permit Finaled | 2/28/2019 | 2/28/2019 | 2/28/2019 3:42:30 PM | P | PASS |
|
|
|
BLD18-02471
| BLD-Framing/Rough-in | 2/28/2019 | 2/28/2019 | 2/28/2019 1:37:21 PM | P | FAIL |
|
|
Contact is Jim Hibbard. Please give me 30 minute heads up. As requested by Mike the lid in the new office area before cover. Phone #: ###-#### Inspection requested via web by James Hibbard. Extension at top of existing rated wall needs to be non combustible or fire rated wood. Ar behind built up area needs to have been sheetrocked with all penetrations firecaulked.
|
BLD17-04612
| BLD-Footing | 2/27/2019 | 2/28/2019 | 2/28/2019 1:17:26 PM | P | NR |
|
|
Jeff Phone #: ###-####. Footings at mid landing need min 24 inch for frost depth.
|
BLD18-02176
| BLD-Footing | 2/25/2019 | 2/28/2019 | 2/28/2019 10:20:24 AM | A | CANC |
|
|
early am Phone #: ###-#### Inspection requested via web by Steve Mitchell
|
BLD18-04577
| BLD-Framing/Rough-in | 2/27/2019 | 2/28/2019 | 2/28/2019 9:30:56 AM | A | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Complete lateral bracing on A3, A4, A6 and A7 trusses. Ok to insulate. Correction notice posted.
|
BLD18-04577
| BLD-Wall Bracing | 2/27/2019 | 2/28/2019 | 2/28/2019 9:29:24 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD19-00470
| BLD-Footing | 2/27/2019 | 2/28/2019 | 2/28/2019 8:37:47 AM | A | FAIL |
|
|
Ned Phone #: ###-####. Footings full of water, need longer lap length fromm existing to new, 36 inches per the engineering.
|