BLD18-04246
| BLD-Final | 2/6/2019 | 2/7/2019 | 2/8/2019 7:45:05 AM | P | CANC |
|
|
Tony Phone #: ###-####
|
BLD18-02176
| BLD-Footing | 2/2/2019 | 2/7/2019 | 2/7/2019 4:03:12 PM | A | DEFR |
|
|
Early AM please Phone #: ###-#### Inspection requested via web by Steve Mitchell
|
BLD18-03251
| BLD-Framing/Rough-in | 2/7/2019 | 2/7/2019 | 2/7/2019 3:20:44 PM | P | PASS |
|
|
Framing and shear wall inspection. Phone #: ###-#### Inspection requested via web by Jimmie Miller. Exterior steel stud framed shear walls/holdowns and wind girts ok.
|
BLD18-02281
| BLD-Final | 2/7/2019 | 2/7/2019 | 2/7/2019 2:36:06 PM | P | PART |
|
|
Julian Phone #: ###-####. Ok for temp occ. to use the new sevice/lube addition. Still some storefront work and plan mod for the deletion of the storage room.
|
BLD19-00275
| BLD-Foundation | 2/7/2019 | 2/7/2019 | 2/7/2019 1:25:28 PM | P | PASS |
|
|
wall-Tim Phone #: ###-####
|
BLD18-04513
| BLD-Framing/Rough-in | 2/6/2019 | 2/7/2019 | 2/7/2019 1:16:41 PM | P | PASS |
|
|
Contact: Jason Curley ###-#### Phone #: ###-#### Inspection requested via web by BRS Permitting
|
BLD17-04447
| BLD-Framing/Rough-in | 2/6/2019 | 2/7/2019 | 2/7/2019 11:29:42 AM | A | PASS |
|
|
Hello Mike, we want to look at 1 hour assembly of elevator machine room,, shaft wall Inspection requested via web by Jim Carriveau. Interior layer of 1 inch saft board for 1 hr. ceiling asembly in elevator machine room.
|
BLD18-01425
| BLD-Framing/Rough-in | 2/6/2019 | 2/7/2019 | 2/7/2019 10:56:21 AM | A | PART |
|
|
exterior framing /// James Phone #: ###-####. Exterior steel stud framed walls at areas D and E, work is still in progess. Still needs to repair headers fro areas C .
|
BLD18-03772
| BLD-Energy code compliance | 2/6/2019 | 2/7/2019 | 2/7/2019 9:09:24 AM | A | PASS |
|
|
TJ Phone #: ###-####
|
MIS19-00032
| Set Bond Amount | 2/6/2019 | 2/7/2019 | 2/7/2019 8:51:12 AM | A | DONE |
|
|
Victor Phone #: ###-####. Demo bond set at $4,300.00 doaalars.
|
ESC18-00966
| Site Final | 2/7/2019 | 2/7/2019 | 2/7/2019 8:29:52 AM | A | DONE |
|
|
|
ESC18-00966
| DOC - Permit Finaled | 2/7/2019 | 2/7/2019 | 2/7/2019 8:29:46 AM | P | PASS |
|
|
|
BLD18-02280
| BLD-Final | 2/6/2019 | 2/7/2019 | 2/7/2019 8:29:34 AM | A | PASS |
|
|
garage code 7530 Phone #: ###-#### Inspection requested via web by Rustin Ray
|
BLD18-02280
| DOC - Permit Finaled | 2/7/2019 | 2/7/2019 | 2/7/2019 8:29:25 AM | P | PASS |
|
|
|
BLD18-02280
| BLD-Blower Door Test Results | 2/7/2019 | 2/7/2019 | 2/7/2019 8:28:50 AM | A | DONE |
|
|
4.75 ACH @ 50pa
|