Inspections for the day of: Wednesday, April 26, 2017.
Number of inspections: 20
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMike Jordan
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD16-02899 BLD-Framing/Rough-in4/25/20174/26/20174/26/2017 5:33:48 PMPCANC
BLD17-00503 BLD-Wall cover4/26/20174/26/20174/26/2017 5:33:43 PMPPASS
Contact: Hunter Gomez.. Late PM; pending passing Mech. Pressure Test Inspection Phone #: ###-#### Inspection requested via web by Mike McHargue
BLD16-03327 BLD-Ceiling Grid Inspection4/26/20174/26/20174/26/2017 3:15:13 PMPPASS
Harvey Phone #: ###-####. Base layer 5/8 type x rock ok on 1hr. roof/ceiling assembly.
BLD17-00861 BLD-Final4/26/20174/26/20174/26/2017 2:49:00 PMPPASS
Dan Phone #: ###-####
BLD17-00861 DOC - Permit Finaled4/26/20174/26/20174/26/2017 2:48:50 PMPPASS
BLD16-04597 BLD-Ceiling Grid Inspection4/26/20174/26/20174/26/2017 2:36:44 PMPPASS
Phone #: ###-#### Inspection requested via web by Richard Wilson
BLD16-01010 BLD-Final4/25/20174/26/20174/26/2017 2:17:12 PMPPASS
Mike, I called Meridian Plumbing after we talked and the final plumbing inspection is supposed to take place in the morning. I was hoping you could do the final-final in the afternoon. Thanks so much for your time Phone #: ###-#### Inspection requested via web by Dale Hinman
BLD16-01010 DOC - Permit Finaled4/26/20174/26/20174/26/2017 2:16:59 PMPPASS
BLD17-00463 BLD-Framing/Rough-in4/26/20174/26/20174/26/2017 1:40:26 PMPFAIL
Phone #: 2085156235 >> Inspection requested via mobile web by Brian Rodriguez . Needs to complete foam seal prior to framing inspection. Roll block floor joist at glulam in garage. Provide anchor bolts in garage on bearing wall. Correction notice posted.
BLD17-00762 BLD-Footing4/26/20174/26/20174/26/2017 1:37:41 PMPNR
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo lira
BLD16-02899 BLD-Framing/Rough-in4/25/20174/26/20174/26/2017 11:58:02 AMACANC
BLD17-00503 BLD-Energy code compliance4/25/20174/26/20174/26/2017 10:44:08 AMANR
Mid-Late Morning. Contact: Hunter Gomez Phone #: ###-#### Inspection requested via web by Mike McHargue. Needs to resolve mech. isssues.
BLD17-00503 BLD-Wall cover4/25/20174/26/20174/26/2017 10:41:27 AMACANC
Mid-Late Morning. Contact: Hunter Gomez Phone #: ###-#### Inspection requested via web by Mike McHargue
BLD17-00585 BLD-Other4/25/20174/26/20174/26/2017 10:13:17 AMAPASS
Mark Phone #: ###-####. Firestop at 1hr. floor asembly ok.
BLD16-01944 BLD-Final4/25/20174/26/20174/26/2017 9:59:25 AMAFAIL
Bill Phone #: ###-####. Install exterior handrails, install all missing side lights, provide final letter from special inspection agency.
MIS17-00129 BLD-Conference4/24/20174/26/20174/26/2017 9:31:41 AMADONE
please see if a tenant is in building-there are no C of O''s-can you please verify-questions contact Bev M.// status review per 415. Spoke to tenants, sundance is getting the drwings ready from the architect and will submit to plan review.
BLD16-02649 BLD-Other4/25/20174/26/20174/26/2017 8:58:24 AMAPASS
Pat-RC1 Phone #: ###-####
BLD17-00238 BLD-Framing/Rough-in4/25/20174/26/20174/26/2017 8:35:15 AMAPASS
would like call ahead; Joseph Phone #: ###-####
BLD17-00238 BLD-Energy code compliance4/26/20174/26/20174/26/2017 8:35:14 AMAPASS
would like call ahead; Joseph Phone #: ###-####
BLD17-00032 BLD-Final4/24/20174/26/20174/25/2017 2:39:24 PMPNR