Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD20-00440 BLD-Final4/27/20204/29/20204/29/2020 1:47:59 PMPPASS
Lloyd ***cleared** Phone #: ###-####
BLD20-00440 DOC - Permit Finaled4/29/20204/29/20204/29/2020 1:47:48 PMPPASS
Notified contractor that no occupancy was allowed under this permit. Appears that Sylvan learning center is goin to move in. A seperate permit is required for occupancy. A letter of completion was issued.
BLD20-00639 BLD-Final4/29/20204/29/20204/29/2020 1:13:11 PMPPASS
screened // Brandy Phone #: ###-####
BLD20-00639 DOC - Permit Finaled4/29/20204/29/20204/29/2020 1:13:04 PMPPASS
BLD18-01027 BLD-Framing/Rough-in4/9/20204/29/20204/29/2020 12:49:38 PMACANC
BLD18-04519 BLD-Framing/Rough-in4/29/20204/29/20204/29/2020 10:51:59 AMANR
Ceiling drops for cover in Building 10 (12 units), late as possible this morning. Phone #: ###-#### Inspection requested via web by Bob Goodwin. Stiil needs mech. rough in inspection. electrical rough in inspection has failed for all units.
BLD20-01178 BLD-Framing/Rough-in4/29/20204/29/20204/29/2020 10:50:40 AMAPART
Phone #: ###-#### Inspection requested via web by Todd Landvatter. Interior steel stud framed walls ok. pending electrical rough in inspection.
BLD19-02464 BLD-Energy code compliance4/28/20204/29/20204/29/2020 10:22:16 AMAPASS
Ed *cleared* Phone #: ###-####. 2nd. floor North half.
BLD18-04318 BLD-Ceiling Grid Inspection4/28/20204/29/20204/29/2020 9:36:35 AMAFAIL
Phone #: ###-#### Inspection requested via web by Clint Hogwood. Provide UL listed 1 hr. ceiling grid system in 1hr. corridors. Also appears that doors and glazing have been switched out and ratings not maintained. Also noted several apeas were grid system is not completed. Correction notice was issued.
BLD19-04980 BLD-Foundation4/28/20204/29/20204/29/2020 8:42:41 AMAPART
Gene Pour time at 12 Phone #: ###-####. East and west step footings and north footing line. Work in progress. ok to place concrete pending special inspection.
BLD19-00803 BLD-Final4/27/20204/29/20204/28/2020 10:14:13 PMACANC