Inspections for the day of: Wednesday, July 10, 2019.
Number of inspections: 24
Percentage of inspections complete: 71 %
Percentage of inspections not complete: 29 %
Contact Information
InspectorMike Jordan
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD19-01398 BLD-Footing7/3/20197/3/2019 P 
Kenny-footing insulation Phone #: ###-####
BLD19-01373 BLD-Footing7/3/20197/3/2019 P 
Kenny-footing insulation Phone #: ###-####
BLD19-01403 BLD-Footing7/3/20197/3/2019 P 
Kenny-footing insulation Phone #: ###-####
BLD19-01402 BLD-Footing7/3/20197/3/2019 P 
Kenny-footing insulation Phone #: ###-####
BLD19-01401 BLD-Footing7/3/20197/3/2019 P 
Kenny-footing insulation Phone #: ###-####
BLD19-01400 BLD-Footing7/3/20197/3/2019 P 
Kenny-footing insulation Phone #: ###-####
BLD19-01399 BLD-Footing7/3/20197/3/2019 P 
Kenny-footing insulation Phone #: ###-####
BLD17-04653 BLD-Final7/10/20197/10/20197/10/2019 4:41:49 PMPPASS
ADA hardware has been provided for the barn door. OK for perm occ.
BLD18-02407 BLD-Foundation7/10/20197/10/20197/10/2019 4:33:47 PMPPASS
Doug - after 2pm Phone #: ###-####. Footings ok. City approved plans on site. Noted that building pad appears to be built up 3/4 inch road mix. Footings appear to be on undisturb native soils. Called and have left message with owner, Micheal Moore, to call me back to discuss pad and if compaction testing was completed.
ESC19-00175 Site Final7/10/20197/10/20197/10/2019 3:22:23 PMPDONE
ESC19-00175 DOC - Permit Finaled7/10/20197/10/20197/10/2019 3:22:15 PMPPASS
BLD19-00486 BLD-Final7/10/20197/10/20197/10/2019 3:22:05 PMPPASS
Tim Phone #: ###-####
BLD19-00486 DOC - Permit Finaled7/10/20197/10/20197/10/2019 3:21:56 PMPPASS
BLD17-04653 BLD-Final7/10/20197/10/20197/10/2019 3:03:53 PMPPART
Phone #: ###-#### Inspection requested via web by David Sferle. OK for temp occ. Still needs to provide ADA hardware for barn door.
BLD19-01807 BLD-Framing/Rough-in7/10/20197/10/20197/10/2019 2:36:47 PMPFAIL
Call 20 ahead- John Phone #: ###-####. Needs to provide the city set of approved plans.
BLD17-00320 BLD-Energy code compliance7/10/20197/10/20197/10/2019 1:57:57 PMPPASS
Steven Phone #: ###-####
BLD19-01305 BLD-Final7/9/20197/10/20197/10/2019 11:30:31 AMAPASS
David Phone #: ###-####
BLD19-01305 DOC - Permit Finaled7/10/20197/10/20197/10/2019 11:30:23 AMPPASS
BLD19-00495 BLD-Final7/10/20197/10/20197/10/2019 11:02:16 AMAFAIL
door code is 2468 Phone #: ###-#### Inspection requested via web by Joel Hirtle. Provide blower door report and results and post. Complete install of vapor barrier in crawl space.
BLD19-00595 BLD-Final7/10/20197/10/20197/10/2019 10:49:30 AMAPEND
garage door code is 2468 Phone #: ###-#### Inspection requested via web by Joel Hirtle. Needs blower door test results and post. Everything else ok.
BLD18-04286 BLD-Conference7/9/20197/10/20197/10/2019 9:55:00 AMADONE
9:30 please Glen Phone #: ###-####
BLD19-01925 BLD-Wall Bracing7/9/20197/10/20197/10/2019 9:30:54 AMAPASS
Juan Phone #: ###-####
BLD19-00803 BLD-Framing/Rough-in7/10/20197/10/20197/10/2019 8:55:51 AMAPASS
Phone #: ###-#### Inspection requested via web by Scott Zierler
BLD19-00154 BLD-Framing/Rough-in7/9/20197/10/20197/10/2019 8:41:58 AMAPASS
John Phone #: ###-####. All corrections have been made. Ok to insulate.