Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD17-02415 BLD-Aging Inspection7/16/20187/16/20187/16/2018 4:49:30 PM PEND
BLD17-02416 BLD-Aging Inspection7/16/20187/16/20187/16/2018 4:49:11 PM PEND
BLD18-01875 BLD-Foundation7/13/20187/16/20187/16/2018 4:46:37 PMPPASS
Chuck Phone #: ###-#### ( please call with results )
BLD18-01424 BLD-Framing/Rough-in7/15/20187/16/20187/16/2018 4:46:24 PMPNR
Phone #: ###-#### Inspection requested via web by Kelly Stover. Mech. rough in inspection has failed.
BLD18-02363 BLD-Final7/13/20187/16/20187/16/2018 4:42:19 PMPPASS
Abdi Phone #: ###-####. O for perm occ.
BLD18-01278 BLD-Other7/16/20187/16/20187/16/2018 4:41:48 PMPPASS
Gene-floor insulation Phone #: ###-####. Floor framing, insulation and vapor barrier ok.
BLD18-02293 BLD-Energy code compliance7/16/20187/16/20187/16/2018 3:17:38 PMPPASS
call 20 minute before to meet // WIll Phone #: ###-####
BLD18-01608 BLD-Final7/13/20187/16/20187/16/2018 3:11:53 PMPPASS
call 20 mins head -Ryan Phone #: ###-####
BLD18-01608 DOC - Permit Finaled7/16/20187/16/20187/16/2018 3:11:45 PMPPASS
BLD18-01927 BLD-Foundation7/16/20187/16/20187/16/2018 2:29:07 PMPPASS
Mile Phone #: ###-####
BLD18-00795 BLD-Footing7/16/20187/16/20187/16/2018 2:15:53 PMPPART
The concrete pour is scheduled for 130 pm. Phone #: ###-#### Inspection requested via web by KJ Savaria. Placmemnt completed. Special inspecor on site. Frost wall for storage unit attached to office ok.
BLD18-01191 BLD-Foundation7/13/20187/16/20187/16/2018 2:01:53 PMPPART
Requesting a 12-12:30pm foundation inspection with concrete at 1pm. Phone #: ###-#### Inspection requested via web by Markus Schlegel. Perimeter stemwalls, special inspector on site. Placement in progress when on site.
BLD16-04511 BLD-Framing/Rough-in7/16/20187/16/20187/16/2018 1:45:38 PMPFAIL
Phone #: ###-#### Inspection requested via web by Sam Brown. Complete firblocking of mech. shaft upstairs. Nail off h2.5. Renail osb and jack trusses to paralam downstairs.
BLD16-04502 BLD-Energy code compliance7/16/20187/16/20187/16/2018 1:27:41 PMPNR
Phone #: ###-#### Inspection requested via web by Sam Brown
BLD16-04502 BLD-Framing/Rough-in7/16/20187/16/20187/16/2018 1:27:27 PMPFAIL
Phone #: ###-#### Inspection requested via web by Sam Brown. Needs to complete install of SDS screws and nail of h2.5
BLD16-04501 BLD-Energy code compliance7/16/20187/16/20187/16/2018 1:26:33 PMPPASS
Phone #: ###-#### Inspection requested via web by Sam Brown
BLD16-04501 BLD-Framing/Rough-in7/16/20187/16/20187/16/2018 1:26:12 PMPPASS
Phone #: ###-#### Inspection requested via web by Sam Brown
GRD17-00084 GRD-Final7/13/20187/16/20187/16/2018 11:48:56 AMAPASS
Tony Phone #: ###-####
BLD18-02457 BLD-Foundation7/12/20187/16/20187/16/2018 11:19:20 AMAPASS
Manny Phone #: ###-####
BLD18-02457 BLD-Footing7/12/20187/16/20187/16/2018 11:19:05 AMAPASS
Manny Phone #: ###-####
BLD18-02306 BLD-Framing/Rough-in7/13/20187/16/20187/16/2018 11:05:16 AMANR
Call Tim 30 minutes prior for accesa Phone #: ###-#### Inspection requested via web by Timothy Gammill. Neeeds electrical rough in inspection and plumbing rough in inspection has failed.
BLD17-00339 BLD-Final7/13/20187/16/20187/16/2018 10:36:31 AMAPART
Ross is the super. Last item to be reviewed is ceiling tile. Thank you! Phone #: ###-#### Inspection requested via web by Jackie Phelps. Ok for temp occ. while the remainder of the flooring and engineering room are completed.
BLD17-04237 BLD-Final7/13/20187/16/20187/16/2018 10:24:57 AMAPEND
Vince Phone #: ###-####. Provide blower door test results and post. everything else ok.
BLD18-01152 BLD-Framing/Rough-in7/13/20187/16/20187/16/2018 10:03:06 AMAFAIL
Shawn Phone #: ###-####. Nail off simpson hangars in garage. Provide tempered glazing at window bottom of stairs. Fire block flue cahse 2nd floor ceiling. fireblock 1st floor ceiling at mech chase. Aslo had contractor remove portions of tyvek to spot check wall bracing and verified all blocking. Correction notice posted. Ok to insulate.
BLD18-02429 BLD-Framing/Rough-in7/13/20187/16/20187/16/2018 9:06:12 AMAPASS
Santiago Phone #: ###-####
BLD18-02148 BLD-Framing/Rough-in7/16/20187/16/20187/16/2018 8:46:25 AMAPART
Work in progress on installing rigid insulation, gluing of roof board.
BLD16-04502 BLD-Energy code compliance7/16/20187/16/20187/16/2018 6:35:43 AMACANC
Phone #: ###-#### >> Inspection requested via web by Sam Brown Inspection cancelled from web by: Sam Brown
BLD16-04502 BLD-Framing/Rough-in7/16/20187/16/20187/16/2018 6:35:41 AMACANC
Phone #: ###-#### >> Inspection requested via web by Sam Brown Inspection cancelled from web by: Sam Brown
BLD16-04501 BLD-Energy code compliance7/16/20187/16/20187/16/2018 6:35:39 AMACANC
Phone #: ###-#### >> Inspection requested via web by Sam Brown Inspection cancelled from web by: Sam Brown
BLD16-04501 BLD-Framing/Rough-in7/16/20187/16/20187/16/2018 6:35:37 AMACANC
Phone #: ###-#### >> Inspection requested via web by Sam Brown Inspection cancelled from web by: Sam Brown