Inspections for the day of: Monday, July 17, 2017.
Number of inspections: 23
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMike Jordan
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD17-00215 BLD-Final7/14/20177/17/20177/17/2017 4:34:53 PMPNR
Brian Gray Phone #: ###-####-FYI no health dept sign off yet-schduled tomorrow. Needs to remove ceiling tile for grid inspection and post occ. load sign
MIS16-00030 MIS-Aging Inspection7/17/20177/17/20177/17/2017 3:48:00 PM DONE
MIS16-00030 DOC - Permit Finaled7/17/20177/17/20177/17/2017 3:47:51 PMPPASS
Mech. and plumbing finals were passed.
MIS16-00016 MIS-Aging Inspection7/17/20177/17/20177/17/2017 3:47:02 PM DONE
MIS16-00016 DOC - Permit Finaled7/17/20177/17/20177/17/2017 3:46:51 PMPPASS
A building permit was issued in 2010.
ESC17-00038 Site Final7/17/20177/17/20177/17/2017 3:45:51 PMPDONE
ESC17-00038 DOC - Permit Finaled7/17/20177/17/20177/17/2017 3:45:44 PMPPASS
BLD17-00089 BLD-Final7/17/20177/17/20177/17/2017 3:45:33 PMPPASS
Colby Phone #: ###-####
BLD17-00089 DOC - Permit Finaled7/17/20177/17/20177/17/2017 3:45:25 PMPPASS
BLD17-01328 BLD-Framing/Rough-in7/17/20177/17/20177/17/2017 3:06:34 PMPPASS
Mike Phone #: ###-####
BLD17-00612 BLD-Final7/16/20177/17/20177/17/2017 2:43:57 PMPPEND
Please call Nic a half-hour before inspection. Phone #: ###-#### Inspection requested via web by Nic van Diepen. Architect to provide letter to building official for possible alternate for flush mounted locks on B occ. with 68 occupant load. Everything else ok.
BLD16-04253 BLD-Framing/Rough-in7/17/20177/17/20177/17/2017 2:05:32 PMPPASS
Phone #: ###-#### Inspection requested via web by Darius Saxton. Interior steel stud framed walls ok on north half of building.
BLD17-02295 BLD-Energy code compliance7/17/20177/17/20177/17/2017 1:21:18 PMPPASS
Kurt Phone #: ###-####
BLD17-02295 BLD-Framing/Rough-in7/17/20177/17/20177/17/2017 1:21:02 PMPPASS
Kurt Phone #: ###-####
BLD17-00830 BLD-Framing/Rough-in7/14/20177/17/20177/17/2017 11:31:32 AMACANC
Colby Phone #: ###-####
ESC17-00658 Site Final7/17/20177/17/20177/17/2017 10:38:07 AMADONE
ESC17-00658 DOC - Permit Finaled7/17/20177/17/20177/17/2017 10:37:58 AMPPASS
BLD17-01648 BLD-Final7/14/20177/17/20177/17/2017 10:37:49 AMAPASS
Phone #: ###-#### Inspection requested via web by Timothy Gammill
BLD17-01648 DOC - Permit Finaled7/17/20177/17/20177/17/2017 10:37:41 AMPPASS
BLD17-00830 BLD-Energy code compliance7/17/20177/17/20177/17/2017 10:23:41 AMAPASS
Colby Phone #: ###-####
BLD17-00763 BLD-Footing7/13/20177/17/20177/17/2017 10:03:29 AMAPASS
MTI to Insp rebar and test concrete at line 2 west. Concrete scheduled for noon Monday. Thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls. Footings on gridlines 1 and 2 from grids A to H. Will have special inspection.
BLD17-00729 BLD-Foundation7/14/20177/17/20177/17/2017 9:05:28 AMAPART
Pour 11 // Mike Phone #: ###-####. Work in progress on cmu stemwall, permiter walls from top of footing to finish floor. Will have special inspection.
BLD17-01707 BLD-Framing/Rough-in7/14/20177/17/20177/17/2017 8:33:17 AMAPASS
Mark Phone #: ###-####