Inspections for the day of: Tuesday, July 17, 2018.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMike Jordan
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD18-01969 BLD-Final7/16/20187/17/20187/17/2018 3:28:42 PMPNR
Phone #: ###-#### Inspection requested via web by BRS Permitting. Needs electrical final.
MIS18-00254 BLD-Conference7/3/20187/17/20187/17/2018 3:06:51 PMACANC
New address suite 100 created by addressing department. Renting out separate office space. Need CO?/// check on status
BLD18-02020 BLD-Foundation7/17/20187/17/20187/17/2018 3:04:30 PMPPASS
Chris-stem wall Phone #: ###-####
BLD18-02249 BLD-Footing7/16/20187/17/20187/17/2018 1:45:41 PMPPASS
Please come for footing inspection at 3pm Phone #: ###-#### Inspection requested via web by Jason Schultz
BLD18-01709 BLD-Wall Bracing7/16/20187/17/20187/17/2018 12:20:55 PMAPASS
Bart Phone #: ###-####
BLD18-01221 BLD-Framing/Rough-in7/16/20187/17/20187/17/2018 11:57:47 AMANR
Dan Phone #: ###-####. Needs to complete airseal first.
BLD18-02494 BLD-Final7/16/20187/17/20187/17/2018 11:32:56 AMADONE
Roof final Phone #: ###-#### Inspection requested via web by Kyle Morgan
BLD18-02494 DOC - Permit Finaled7/17/20187/17/20187/17/2018 11:32:47 AMPPASS
All work appeared to be done in accordance with local codes and ordinances.
BLD18-02495 BLD-Final7/16/20187/17/20187/17/2018 11:31:03 AMADONE
Roof final Phone #: ###-#### Inspection requested via web by Kyle Morgan
BLD18-02495 DOC - Permit Finaled7/17/20187/17/20187/17/2018 11:31:03 AMPPASS
All work appeared to be done in accordance with local codes and odinances.
BLD18-00829 BLD-Footing7/16/20187/17/20187/17/2018 8:36:05 AMANR
Jesse Phone #: ###-####. No one on site. no plans. looks like excavation not deep enough ? will need to reschedule.
BLD18-01191 BLD-Other7/16/20187/17/20187/17/2018 12:00:00 AMACANC
Requesting a conference and subsequent inspection on the storm water system and plumbing underground for the inspector assigned to this project. Work will begin 7/17 and will be near complete 7/20. Please advise.
A voice mail message was left with Brian Murphy on 7/13.
Thank you. Phone #: ###-#### >> Inspection requested via web by Markus Schlegel