Inspections for the day of: Tuesday, July 2, 2019.
Number of inspections: 22
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMike Jordan
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MIS18-00319 MIS-Aging Inspection7/2/20197/2/20197/3/2019 2:59:49 PM PASS
BLD19-01394 BLD-Foundation7/1/20197/2/20197/2/2019 4:02:48 PMPPART
Kenny-slab on grad rebar Phone #: ###-####
BLD19-01393 BLD-Foundation7/1/20197/2/20197/2/2019 4:02:37 PMPPART
Kenny-slab on grad rebar Phone #: ###-####
BLD19-01392 BLD-Foundation7/1/20197/2/20197/2/2019 4:02:26 PMPPART
Kenny-slab on grad rebar Phone #: ###-####
BLD19-01391 BLD-Foundation7/1/20197/2/20197/2/2019 4:02:15 PMPPART
Kenny-slab on grad rebar Phone #: ###-####
BLD19-01390 BLD-Foundation7/1/20197/2/20197/2/2019 4:02:04 PMPPART
Kenny-slab on grad rebar Phone #: ###-####
BLD19-01389 BLD-Foundation7/1/20197/2/20197/2/2019 4:01:52 PMPPART
Kenny-slab on grad rebar Phone #: ###-####
BLD19-01374 BLD-Foundation7/1/20197/2/20197/2/2019 4:01:41 PMPPART
Kenny-slab on grad rebar Phone #: ###-####
BLD19-01394 BLD-Concrete7/1/20197/2/20197/2/2019 4:01:24 PMPPART
Brandon Phone #: ###-####. Interior thickend footings.
BLD19-01393 BLD-Concrete7/1/20197/2/20197/2/2019 4:01:06 PMPPART
Brandon Phone #: ###-####. Interior thickend footings.
BLD19-01392 BLD-Concrete7/1/20197/2/20197/2/2019 4:00:48 PMPPART
Brandon Phone #: ###-####. Interior thickend footings.
BLD19-01391 BLD-Concrete7/1/20197/2/20197/2/2019 4:00:32 PMPPART
Brandon Phone #: ###-####. Interior thickend footings.
BLD19-01390 BLD-Concrete7/1/20197/2/20197/2/2019 4:00:07 PMPPART
Brandon Phone #: ###-####. Interior thickend footings.
BLD19-01389 BLD-Concrete7/1/20197/2/20197/2/2019 3:59:41 PMPPART
Brandon Phone #: ###-####. Interior thickend footings.
BLD19-01374 BLD-Concrete7/1/20197/2/20197/2/2019 3:59:21 PMPPART
Brandon Phone #: ###-####. Interior thickend footings.
BLD19-01115 BLD-Final7/1/20197/2/20197/2/2019 3:44:43 PMPDONE
Phone #: ###-#### Inspection requested via web by Laurie Hoelscher
BLD19-01115 DOC - Permit Finaled7/2/20197/2/20197/2/2019 3:44:34 PMPPASS
MIS19-00146 BLD-Conference6/18/20197/2/20197/2/2019 2:21:39 PMADONE
A 5 day notice has been issued to submit plans for review and obtain a building permit.
BLD19-01364 BLD-Framing/Rough-in6/27/20197/2/20197/2/2019 1:50:53 PMPFAIL
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Complete lateral bracing on B6, B7 and B8 trusses. Provide additional studs for bearing on A4G and C4G trusses. An electrical rough in inspection has not been completed. DO NOT COVER OR INSULATE. Correction notice posted.
BLD19-01651 BLD-Framing/Rough-in7/1/20197/2/20197/2/2019 11:31:34 AMAPASS
Tony,

Call me before you head this way. I have a lockbox on the back of the building to get in if no one is there. Thanks,

Todd Phone #: ###-#### Inspection requested via web by Todd Kurns
BLD18-03923 BLD-Ceiling Grid Inspection7/1/20197/2/20197/2/2019 11:06:33 AMAPASS
Uri Phone #: ###-####
BLD19-01436 BLD-Footing7/1/20197/2/20197/2/2019 11:06:01 AMAPASS
An AM inspection on this would be the best. Jimmy will be doing the installation and his cell number is ###-####. Thanks. Phone #: ###-#### Inspection requested via web by rich prasch