BLD17-00763
| BLD-Footing | 9/19/2017 | 9/20/2017 | 9/21/2017 9:33:40 AM | P | CANC |
|
|
We anticipate being ready for inspection around 3pm Wednesday and plan to pour trash enclosure ftgs. Thursday am. Note, MTI checked sub grade ok. Thanks Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls
|
BLD17-03203
| BLD-Final | 9/19/2017 | 9/20/2017 | 9/20/2017 4:06:11 PM | P | NR |
|
|
Lex Phone #: ###-####. Fire/life/safety failed.
|
BLD17-01519
| BLD-Final | 9/19/2017 | 9/20/2017 | 9/20/2017 4:05:51 PM | P | NR |
|
|
Jayson Phone #: ###-####. Fire/life/safety failed.
|
BLD17-01088
| BLD-Framing/Rough-in | 9/19/2017 | 9/20/2017 | 9/20/2017 3:46:32 PM | P | PASS |
|
|
Charles Phone #: ###-####. Interior steel stud framed walls , remainderof framing west of engineering room and south of corridor.
|
BLD17-01388
| BLD-Framing/Rough-in | 9/20/2017 | 9/20/2017 | 9/20/2017 3:45:44 PM | P | PASS |
|
|
Ross Phone #: ###-####
|
BLD17-02867
| BLD-Footing | 9/19/2017 | 9/20/2017 | 9/20/2017 1:34:25 PM | P | PASS |
|
|
Chris Phone #: ###-####
|
BLD16-04460
| BLD-Footing | 9/20/2017 | 9/20/2017 | 9/20/2017 1:34:08 PM | P | PASS |
|
|
Manual Phone #: ###-####
|
BLD16-04475
| BLD-Footing | 9/20/2017 | 9/20/2017 | 9/20/2017 1:33:57 PM | P | PASS |
|
|
Manual Phone #: ###-####
|
BLD16-04459
| BLD-Footing | 9/20/2017 | 9/20/2017 | 9/20/2017 1:33:34 PM | P | PASS |
|
|
Manual Phone #: ###-####
|
BLD16-04476
| BLD-Footing | 9/20/2017 | 9/20/2017 | 9/20/2017 1:33:19 PM | P | PASS |
|
|
Manual Phone #: ###-####
|
BLD17-00339
| BLD-Conference | 9/19/2017 | 9/20/2017 | 9/20/2017 11:44:47 AM | A | CANC |
|
|
Moved to pm for framing inspection of arch to tennis courts.
|
BLD16-01757
| BLD-Framing/Rough-in | 9/19/2017 | 9/20/2017 | 9/20/2017 10:32:31 AM | A | PASS |
|
|
Doug Phone #: ###-####. Ok to rock corridors ceilings and wall to plate line only. Also spoke to contractor about the possibilty of insulating that portion of wall above plate line prior to sheet rock.
|
BLD16-04309
| BLD-Wall Bracing | 9/20/2017 | 9/20/2017 | 9/20/2017 10:01:13 AM | A | PASS |
|
|
Exterior Shear Inspection requested via web by Marty Short
|
BLD16-04308
| BLD-Wall Bracing | 9/20/2017 | 9/20/2017 | 9/20/2017 10:00:59 AM | A | PASS |
|
|
Exterior Shear Inspection requested via web by Marty Short
|
BLD17-02745
| BLD-Final | 9/18/2017 | 9/20/2017 | 9/20/2017 9:25:14 AM | A | PASS |
|
|
Requests first thing in AM - Clifford Phone #: ###-####
|
BLD17-02745
| DOC - Permit Finaled | 9/20/2017 | 9/20/2017 | 9/20/2017 9:25:05 AM | P | PASS |
|
|
|
BLD17-02745
| BLD-Framing/Rough-in | 9/20/2017 | 9/20/2017 | 9/20/2017 9:24:57 AM | A | PASS |
|
|
Requests first thing in AM - Clifford Phone #: ###-####
|
BLD17-01476
| BLD-Final | 9/19/2017 | 9/20/2017 | 9/20/2017 8:44:30 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Candyce Moss
|
BLD17-01476
| DOC - Permit Finaled | 9/20/2017 | 9/20/2017 | 9/20/2017 8:44:30 AM | P | PASS |
|
|
|
BLD17-02481
| BLD-Final | 9/19/2017 | 9/20/2017 | 9/20/2017 8:22:10 AM | A | NR |
|
|
Eric-please call to meet Phone #: ###-####. Provide the panic hardware as noted on the plans. Life/safety final failed as well.
|
BLD17-02350
| BLD-Framing/Rough-in | 9/19/2017 | 9/20/2017 | 9/20/2017 8:21:18 AM | A | NR |
|
|
Phone #: ###-#### Inspection requested via web by Tom Wells. Will insulate and then call for inspection.
|