Inspections for the day of: Friday, September 7, 2018.
Number of inspections: 19
Percentage of inspections complete: 95 %
Percentage of inspections not complete: 5 %
Contact Information
InspectorMike Jordan
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD18-00229 BLD-Framing/Rough-in9/4/20189/4/2018 P 
Jerimy Phone #: ###-####
BLD18-00776 BLD-Footing9/6/20189/7/20189/7/2018 3:51:36 PMPPART
Charlie Phone #: ###-####. Perimeter footings. Noted insufficient clearances from bottom rebar. Will have special inspection. Special inspector to verify correction. Placement will be on Monday Sept. 10th.
BLD18-00313 BLD-Conference9/7/20189/7/20189/7/2018 3:46:44 PMPPASS
TJ Phone #: ###-####. Ok for perm occ.
BLD15-00210 BLD-Framing/Rough-in9/6/20189/7/20189/7/2018 3:41:55 PMPPASS
James Phone #: ###-####
BLD15-00210 BLD-Energy code compliance9/7/20189/7/20189/7/2018 3:39:34 PMPPASS
James Phone #: ###-####
BLD17-02185 BLD-Ceiling Grid Inspection9/7/20189/7/20189/7/2018 3:34:55 PMPPASS
dale Phone #: ###-####
BLD18-02848 BLD-Foundation9/6/20189/7/20189/7/2018 3:34:36 PMPPASS
Please make every effort to be here 1pm - 2pm so we can pour after inspection Inspection requested via web by Steven Shehan
MIS18-00350 BLD-Conference9/7/20189/7/20189/7/2018 10:54:34 AMAPASS
MIS18-00350 DOC - Permit Finaled9/7/20189/7/20189/7/2018 10:54:27 AMPPASS
Panel mounts have been installed at this time. Appears no other work has been done at this time. No one on site working.
BLD18-02304 BLD-Footing9/6/20189/7/20189/7/2018 10:29:17 AMAPART
jason Phone #: ###-####. Perimeter footings. Work in progress on installing vertical reinforcement. Ok to place concrete after special inspection has approved footings.
BLD18-02488 BLD-Framing/Rough-in9/4/20189/7/20189/7/2018 9:58:23 AMAPASS
Tom Phone #: ###-####
BLD18-02517 BLD-Framing/Rough-in9/4/20189/7/20189/7/2018 9:58:13 AMAPASS
Tom Phone #: ###-####
BLD18-02507 BLD-Final9/5/20189/7/20189/7/2018 9:46:04 AMAPEND
Please call ahead for access - Whitney Phone #: ###-####. Will be ok for occ. once plumbing issues have been resolved and plumbing signs perm. occ.
MIS18-00349 BLD-Conference9/6/20189/7/20189/7/2018 9:30:20 AMAPASS
report of reroof without permit
MIS18-00349 DOC - Permit Finaled9/7/20189/7/20189/7/2018 9:30:13 AMPPASS
A roofing permit has been issued.
BLD17-00566 BLD-Final9/6/20189/7/20189/7/2018 9:28:34 AMAFAIL
Please call; 30 min prior to inspection Phone #: ###-#### Inspection requested via web by John Saucerman. Provided panic hardware on the south east exit door. Everything else ok.
BLD18-02020 BLD-Energy code compliance9/6/20189/7/20189/7/2018 8:23:08 AMAPASS
call 30 min in advance // John Phone #: ###-####
BLD18-02020 BLD-Framing/Rough-in9/6/20189/7/20189/7/2018 8:22:57 AMAPASS
call 30 min in advance // John Phone #: ###-####
BLD18-00313 BLD-Final9/7/20189/7/20189/7/2018 12:00:00 AMAPASS
TJ - Per MIke J ok for perm occ (BLD- conference) Phone #: ###-####