Inspections for the day of: Thursday, November 15, 2018.
Number of inspections: 14
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD18-02679 FIRE-Final Inspection11/14/201811/15/201811/15/2018 3:26:21 PMPPASS
No fire sprinkler modificaitons, no fire alarm modifications, hood protection is adequate for applainces that are in place, fire extinguisher will be placed in discussed location. Final life fire safety inspection for area of work complete.

Please call so I can meet and unlock the space. Phone #: ###-#### Inspection requested via web by Kirsten Dallmann
FIR18-00617 INSP-Sprinkler Rough-in11/14/201811/15/201811/15/2018 2:40:03 PMPPART
Rough to cover inspection for overhead fire sprinkler piping above grid in area of work complete, approved for cover.

Rough in inspection of 2nd half of Kitchen/Server area. Zack Grasmick is foreman on job. Phone #: ###-#### Inspection requested via web by Brett Lawatch
BLD16-02008 FIRE-Final Inspection11/15/201811/15/201811/15/2018 1:37:11 PMAPART
Per conversations with Ron Johnson, Tim Frost and Lee Meridith items for phase 1 TCO complete.

Items corrected and ready to review for phase 1. Late morning call Adam when heading to site. Thanks. Akj. Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD18-03487 FIRE-Final Inspection11/15/201811/15/201811/15/2018 1:35:59 PMPPASS
No fire sprinklers, no fire alarm modifications, fire extinguisher is placed with current inspection tag, stignage reading "Door to remain unlocked while building is occupied" to be placed before BLD permit final.

Mark Phone #: ###-####
FIR18-00356 INSP-Sprinkler Rough-in11/15/201811/15/201811/15/2018 1:21:39 PMPPASS
Rough to cover inspection for overhead fire sprinkler piping in area of work for phase 2 complete, approved for cover.

Tom Phone #: ###-####
BLD18-01064 FIRE-Conference11/15/201811/15/201811/15/2018 11:54:45 AMADONE
Had a previous conversation with GC about installing office furniture before fire sprinklers and fire alarms are active. Discussed with Ron Johnson, placing of office furniture is not allowed, office furniture has been installed on level 3 after conversation stating that funiture is not to be installed. No other office furniture is authorized. The GC has been notified verbally that no office furniture is to be installed due to the increased fuel load that the furniture presents. If more office furniture is installed after this entry then the project will have a stop work notice placed and the project will be red tagged, this action is supported per conversation with Ron Johnson, Assistant Fire Marshall.
FIR18-00428 INSP-Sprinkler Rough-in11/15/201811/15/201811/15/2018 10:57:38 AMAPASS
Rough to cover inspection for overhead fire sprinkler piping on level 3 complete, level 3 approved for cover.
FIR18-00428 INSP-Sprinkler Rough-in/Hydro11/14/201811/15/201811/15/2018 10:56:19 AMADONE
Hydrostatic test for level 3 and both standpipes witnessed, no pressure loss observed. All but 7 heads complete at time of hydro, hydro for level 3 is complete.



Hydro on 3rd floor and Hydro for stand pipes in all stair wells. Tony Cetani is the Shilo Foreman. Phone #: ###-#### Inspection requested via web by Stan Beus
FIR18-00583 INSP-Sprinkler Rough-in11/14/201811/15/201811/15/2018 10:51:59 AMAPART
Rough to cover inspection for overhead fire sprinkler piping in various areas complete, areas inspected approved for cover.

Tony Cetani is the Shilo Foreman. Phone #: ###-#### Inspection requested via web by Stan Beus
FIR18-00708 INSP-Sprinkler Rough-in11/14/201811/15/201811/15/2018 10:50:13 AMAPART
Rough to cover inspection for overhead fire sprinkler piping located above the hardlids in the east restrooms complete to include corridor, areas inspected approved for cover.

Tony Cetani is the Shilo foreman. Phone #: ###-#### Inspection requested via web by Stan Beus
FIR18-00673 INSP-Sprinkler Rough-in/Hydro11/14/201811/15/201811/15/2018 10:21:25 AMPFAIL
No stamped city approved drawings on site, need city approved drawings to be onsite at all times.

Contact Pablo at ###-#### Phone #: ###-#### Inspection requested via web by Shane Lesteberg
FIR18-00673 INSP-Sprinkler Rough-in11/14/201811/15/201811/15/2018 10:20:59 AMPFAIL
No stamped city approved drawings on site, need city approved drawings to be onsite at all times.

Contact Pablo at ###-#### Phone #: ###-#### Inspection requested via web by Shane Lesteberg
FIR18-00670 INSP-Sprinkler Rough-in11/14/201811/15/201811/15/2018 8:54:25 AMAPART
Rough in inspection for overhead fire sprinkler piping complete, overhead fire sprinkler piping approved for cover. Branch lines under mezzanine are 2 1/2 inch diameter pipe, top of piping is more than 6 inches down from point of attachment at the hangers, need to add sway bracing to branchlines under mezzanine. Will need to provide as-builts showing the addition of the sway bracing and addition of flex heads..

Please call Chris Ford Phone #: ###-#### Inspection requested via web by Jessia Maxwell
FIR18-00718 INSP-Final Inspection11/14/201811/15/201811/14/2018 3:10:08 PMPCANC
Please call Chris Ford Phone #: ###-#### >> Inspection requested via web by Jessia Maxwell Inspection cancelled from web by: Jessia Maxwell