Inspections for the day of: Wednesday, November 28, 2018.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD18-03357 FIRE-Final Inspection11/27/201811/28/201811/28/2018 1:40:59 PMPPASS
No fire sprinklers, no fire alarms, fire exitnguisher is placed with a current inspection tag. Addressing on the sign board is temporary and permenant addressing will be installed when received.

Nicol Phone #: ###-####
FIR18-00883 INSP-Sprinkler Rough-in11/28/201811/28/201811/28/2018 1:37:46 PMPPASS
Rough to cover inspection for underground supply complete, approved for cover. noted that the underground supply was not routed the same as what the print showed due to valve location froim SUEZ, an as built will be required for submittal before final inspection to verify that the correct waterflow will work with the new pipe route, if figures do not work then corrections to the install will be required.

Contact Hunter Anderson ###-#### 30 min Prior to UG RTC insp start please, he would like to do this after 1 or 2 PM today if possible.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
BLD18-04231 FIRE-Final Inspection11/27/201811/28/201811/28/2018 11:19:20 AMAPASS
Previously noted items have been corrected, final life fire safety inspection for TCO complete, permenant C of O will require fire sprinkler modifications.

call ahead if before 9 // Tara Phone #: ###-####
FIR18-00716 INSP-Sprinkler Rough-in11/27/201811/28/201811/28/2018 11:18:11 AMAPART
Tenting inspection for overhead fire sprinkler piping on level 3, 2 north units complete, approved for cover, remaining units on level 3 still require tenting to be installed and inspected.

Gerarrdo is the contact. he would like a rough to cover on the 3rd floor. Phone #: ###-#### Inspection requested via web by Stan Beus
FIR18-00616 INSP-Sprinkler Rough-in11/28/201811/28/201811/28/2018 9:46:44 AMAFAIL
Insulation has fallen off of piping in numerous areas throughout, tenting needs to be corrected and in place before cover can be approved.
FIR18-00616 INSP-Sprinkler Rough-in/Hydro11/27/201811/28/201811/28/2018 9:45:08 AMADONE
Hydrostatic test witnessed with city pressure (No FDC so static pressure from city utility for hydro). No pressure loss observed.

Rough Hydro and Tenting. Please call when you are heading out, thank you! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
FIR18-00583 INSP-Sprinkler Rough-in11/27/201811/28/201811/28/2018 9:22:58 AMADONE
Conference complete

Tony Cetani is the contact and he would like a 2nd floor consultation. Phone #: ###-#### Inspection requested via web by Stan Beus
BLD18-01064 FIRE-Conference11/28/201811/28/201811/28/2018 9:07:17 AMADONE
Noted that office furniture is still being placed on level 3 after GC notification that office furniture was to not be set until active fire protection is in place, no fire sprinklers are active and no fire alarms are active. Floor is being loaded with extra fuel without any active automatic fire protection in place.
FIR18-00883 INSP-Sprinkler Rough-in11/27/201811/28/201811/27/2018 12:04:46 PMACANC
Contact Hunter Anderson ###-#### 30 min Prior to RTC Insp start please.

Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank