Inspections for the day of: Wednesday, December 5, 2018.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR18-00510 INSP-Sprinkler Rough-in/Hydro12/5/201812/5/201812/5/2018 3:28:38 PMPDONE
Hydrostatic test for townhomes witnessed, no pressure loss observed. Noted, now that water has been intruduced to the fire sprinkler system the internal building temperature of the effected areas needs to be maintained at 40 degree or above, if areas drop below 40 degrees then a re-hydro will be required.

Hydro on the town homes. Phone #: ###-#### Inspection requested via web by Sam Ball
FIR18-00308 INSP-Sprinkler Rough-in/Hydro12/5/201812/5/201812/5/2018 1:38:09 PMPDONE
Hydrostatic test for underground supply witnessed, no pressure loss observed.
BLD16-02008 FIRE-Final Inspection12/5/201812/5/201812/5/2018 1:29:37 PMPPART
Life fire safety inspection for Phase 2 TCO complete.

TCO final inspections, phase 2, Loft Units, follow up to walk last week. Please contact Adam when heading to site. Thanks. AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson
FIR18-00686 INSP-Sprinkler Rough-in/Hydro12/4/201812/5/201812/5/2018 1:27:40 PMPPART
Rough in inspection complete for overehad fire sprinkler piping east of the chapel complete, discussed areas for sway brace attachment, hydro for installed section will be completed on 06DEC2018 per conversation with sprinkler fitter on project.

Ron Phone #: ###-####
FIR18-00382 INSP-Sprinkler Rough-in/Hydro12/4/201812/5/201812/5/2018 1:25:55 PMPPART
Hydro was for shell piping, pendants and armovers still need to be installed after finish ceiling, a hydrostatic test will need to be completed after heads are cut in. Rough in inspection for overhead fire sprinkler piping complete, a cover inspection will be required after heads are cut in for cover approval.

Foreman on job is Zack Grasmick. Phone #: ###-#### Inspection requested via web by Brett Lawatch
FIR18-00502 INSP-Final Inspection12/5/201812/5/201812/5/2018 10:59:27 AMPFAIL
Irrigation timer is not hooked to flow switch, no zone wires for irigation are installed so irrigation shutdown cannot be verified. Need to verify irrigation shutdown before permit can be finaled.

Please call Anthony before heading out, thank you! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
FIR18-00610 INSP-Conference12/5/201812/5/201812/5/2018 10:31:33 AMADONE
Access and exit to riser room is acceptable as long as the largest piece of equipment in the room can be removed without obstruction.
FIR18-00610 INSP-Sprinkler Rough-in12/4/201812/5/201812/5/2018 10:28:17 AMACANC
Mike Phone #: ###-####
FIR18-00708 INSP-Sprinkler Rough-in12/4/201812/5/201812/5/2018 9:26:13 AMAPART
Rough in inspection for shell piping complete, a cover inspection will be required after pendant heads/arm overs are installed.

Tony Cetani is the contact and he would like a rough to cover inspection on piping. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus