FIR18-00654
| INSP-Supply line flush | 2/19/2019 | 2/20/2019 | 2/20/2019 2:40:42 PM | P | DONE |
|
|
Undergournd main line flush complete.
Please call chris ford Phone #: ###-#### Inspection requested via web by Jessia Maxwell
|
BLD18-04312
| FIRE-Final Inspection | 2/20/2019 | 2/20/2019 | 2/20/2019 2:40:10 PM | P | FAIL |
|
|
Provide exit signage and emergency lighting on the southside enclosed patio. Provide emergency lighting in corridor between restrooms. Provide signage over the top of the main entry reading "Door to remain unlocked while building is occupied". South door swings the wrong direction for path of travel, need to correct door swing and install panic type door hardware per building fire code review comments. Place fire extinguishers in discussed locations.
Anthony Phone #: ###-####
|
FIR17-00508
| INSP-Final Inspection | 2/20/2019 | 2/20/2019 | 2/20/2019 1:08:13 PM | P | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Gary Gambino Inspection cancelled from web by: Gary Gambino
|
BLD18-04113
| FIRE-Final Inspection | 2/19/2019 | 2/20/2019 | 2/20/2019 11:08:38 AM | A | FAIL |
|
|
FIR permit (FIR18-00963) for fire alarms is still in issued status during the time of entering these notes, FIR permit for fire alarms needs to be completed before life fire safety can be finaled.
Call 20 minutes before // Dan Phone #: ###-####
|
BLD19-00404
| FIRE-Final Inspection | 2/20/2019 | 2/20/2019 | 2/20/2019 8:49:32 AM | P | PASS |
|
|
Previously noted items have been corrected, final life fire safety inspection for area of work complete.
Paul Phone #: ###-####
|
FIR19-00075
| INSP-Sprinkler Rough-in | 2/19/2019 | 2/20/2019 | 2/20/2019 8:48:55 AM | P | PASS |
|
|
Final fire sprinkler inspection for area of work complete.
Raul Phone #: ###-####
|
FIR18-00930
| INSP-Sprinkler Rough-in/Hydro | 2/19/2019 | 2/20/2019 | 2/20/2019 8:47:46 AM | A | CANC |
|
|
Hydrostatic test for overhead fire sprinkler piping in conapy has been cancelled, weather does not permit a hydrostatic test, temperature for hydrostaic tests needs to be maintained at 40 degrees or above for hydro to be accepted.
Zach Phone #: ###-####
|
FIR18-00930
| INSP-Supply line flush | 2/19/2019 | 2/20/2019 | 2/20/2019 8:45:52 AM | A | CANC |
|
|
Inspection request was for a completion on the air test, not a main line flush, this request is cancelled.
air test // Zack Phone #: ###-####
|
FIR18-00930
| INSP-Sprinkler Rough-in/Hydro | 2/20/2019 | 2/20/2019 | 2/20/2019 8:44:43 AM | A | DONE |
|
|
24 hour air test complete with no pressure loss witnessed.
|
FIR19-00107
| INSP-Final Inspection | 2/19/2019 | 2/20/2019 | 2/20/2019 8:43:37 AM | A | PASS |
|
|
Final fire sprinkler inspection for area of work complete.
Payton Phone #: ###-####
|
FIR19-00107
| INSP-Sprinkler Rough-in | 2/20/2019 | 2/20/2019 | 2/20/2019 8:43:10 AM | A | PASS |
|
|
Rough to cover inspection for overhead firte sprinkler piping in area of work complete, approved for cover.
|