Inspections for the day of: Wednesday, March 6, 2019.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR18-00827 INSP-Sprinkler Rough-in/Hydro3/5/20193/6/20193/6/2019 3:31:54 PMADONE
Hydrostatic test for overhead fire sprinkler piping on levels 1, 2 and 3 witnessed, no pressure loss observed.

Gabe Garduno is the contact. This inspection is for a hydro only. Thanks for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
BLD18-02551 FIRE-Final Inspection3/5/20193/6/20193/6/2019 3:31:04 PMPPART
Final inspection for life fire safety inspection is complete, a 45 day TCO is approved by Ron Johnson provided the fire alarm work is completed (see fire alarm comments under FIR19-00078) as-builts are submitted, work performed matches city approved drawings and FIR permit for fire alarms is finaled.

Call 30 mins before Phone #: ###-#### Inspection requested via web by Johnathon McGee
FIR19-00078 INSP-Final Inspection3/6/20193/6/20193/6/2019 3:25:05 PMPPART
Final fire alarm inspection for scope of work is complete. NAC panel is going to be changed per conversation with installing contractor. A follow up inspection will be required after NAC replacement is complete. TCO mis authorized per conversation with Ron Johnson for 45 days contingent on fire alarm completion, to include as-built submittal and approval.

Please call 1/2 hour ahead Phone #: ###-#### Inspection requested via web by Rafe Barrett
FIR18-00714 INSP-Final Inspection3/5/20193/6/20193/6/2019 3:21:31 PMPPART
Final fire alarm inspection is complete provided the as-builts match the added work that was completed. Once as-builts are submitted, approved and matches completed work then permit can be finaled.

Contact is Dirk.

Will not be available AM, must be PM for technician availability. Phone #: ###-#### Inspection requested via web by Morgan Ahten
FIR18-00852 INSP-Final Inspection3/6/20193/6/20193/6/2019 3:18:34 PMPPART
Final fire sprinkler inspection is complete provided the as-builts match the added work that was completed. Once as-builts are submitted, approved and matches completed work then permit can be finaled.

Looking to get T.C.O. submital for stairs threw 3rd to fourth are in Phone #: ###-#### Inspection requested via web by jeremiah robison
FIR19-00047 INSP-Sprinkler Rough-in3/6/20193/6/20193/6/2019 12:02:40 PMPPART
Rough to cover inspection for overhead fire sprinkler piping above hardlids in area of work complete, hardlids approved for cover.

Todd Ketterling is the contact. Thank you for your work! Phone #: ###-#### Inspection requested via web by Stan Beus
FIR18-00544 INSP-Supply line flush3/5/20193/6/20193/6/2019 10:39:45 AMADONE
Underground main line flush witnessed.

Gabe Garduno is the contact. This inspection is for a flush and hydro. Thank you for all that you do! Phone #: ###-#### Inspection requested via web by Stan Beus
FIR18-00828 INSP-Sprinkler Rough-in/Hydro3/5/20193/6/20193/6/2019 10:39:06 AMADONE
Hydrostatic test for overhead fire sprinkler piping on level 3 witnessed, no pressure loss observed.

This is for a hydro only inspection. Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
FIR18-00563 INSP-Sprinkler Rough-in/Hydro3/5/20193/6/20193/6/2019 10:38:12 AMADONE
Hydrostatic test for undergorund supply witnessed, no pressure loss observed.

This is for an underground hydro only. Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
FIR18-00610 INSP-Sprinkler Rough-in3/5/20193/6/20193/6/2019 9:37:46 AMAPART
Rough to cover inspection for level 5 restrooms and elevator lobby complete, approved for cover.

Mike-5th floor Phone #: ###-####