FIR19-00097
| INSP-Sprinkler Rough-in | 3/8/2019 | 3/8/2019 | 3/8/2019 2:06:53 PM | P | PASS |
|
|
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, area of work approved for cover.
Phone #: ###-#### Inspection requested via web by Sam Ball
|
FIR18-00204
| INSP-Final Inspection | 3/8/2019 | 3/8/2019 | 3/8/2019 2:05:32 PM | P | CANC |
|
|
Does not appear as-builts have been reviewed per activities under this permit. After discussion with point of contact, inspection request will be rescheduled for a later date, this request is cancelled per conversation with POC.
Bill Phone #: ###-####
|
BLD19-00731
| FIRE-Final Inspection | 3/8/2019 | 3/8/2019 | 3/8/2019 1:22:24 PM | P | PASS |
|
|
No fire sprinkler modifications, no fire alarm modifications, fire extinguishers are placed with current inspection tags. Final life fire safety inspection complete.
Sherri-please call before you go-Sherri is here at city for a few more mintues Phone #: ###-####
|
BLD18-03600
| FIRE-Final Inspection | 3/8/2019 | 3/8/2019 | 3/8/2019 12:45:51 PM | P | FAIL |
|
|
Fire sprinkler, hood suppression (FIR19-00178 is for the hood suppression) and fire alarm permits are still in issued status and have not had final inspections, FIR permits for fire alarm, fire sprinkler and hood suppression must be inspected and finaled before life fire safety can be completed.
Taylor Phone #: ###-####
|
FIR18-00633
| INSP-Sprinkler Rough-in/Hydro | 3/5/2019 | 3/8/2019 | 3/8/2019 10:42:05 AM | P | PART |
|
|
Only level 3, east side of elevators inspected today, overhead fire sprinkler piping in area D and part of C, east side of elevators on level 3 approved for cover. Building temperature could not be maintained above 40 degrees at time of inspection, no hydrostatic test was performed.
Kenny Caldwell is the contact. This RTC/Hydro is for the 2nd ; 3rd floors. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00461
| INSP-Sprinkler Rough-in | 3/8/2019 | 3/8/2019 | 3/8/2019 9:03:29 AM | A | FAIL |
|
|
Numerous heads are blocked in parking garage due to sewer drain modifications, head coverage will need to be corrected in parking garage to be code compliant.
|
FIR18-00510
| INSP-Sprinkler Rough-in | 3/8/2019 | 3/8/2019 | 3/8/2019 9:01:49 AM | P | FAIL |
|
|
Cover material was installed on 4 before cover inspection was completed, it has already been mentioned (Noted on 17DEC2018 inspection and 25JAN2019 inspection) on other areas of this project that cover inspection has to be performed before cover is approved. All cover material over piping needs to be removed. Numerous heads are blocked in parking garage due to sewer drain modifications, head coverage will need to be corrected in parking garage to be code compliant.
4th;5th floor. Phone #: ###-#### Inspection requested via web by Sam Ball
|