Inspections for the day of: Tuesday, April 2, 2019.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR18-00901 INSP-Conference4/2/20194/2/20194/2/2019 3:05:29 PMPDONE
A second curb valve was installed after SUEZ valve to accomplish underground hydrostatic test, underground held 200psi for 2 hours as required by NFPA 13.

This is inspection to confirm our isolation of the underground from the Suez service and hydro test of UG. It can be completed during hydro test for overhead. We will be on site. Phone #: ###-#### Inspection requested via web by Jeff Packham
FIR18-00901 INSP-Sprinkler Rough-in/Hydro4/2/20194/2/20194/2/2019 3:04:23 PMPDONE
Hydrostatic test for underground supply and overhead fire sprinkler piping witnessed, no pressure loss observed.

Tom Phone #: ###-####
FIR19-00138 INSP-Sprinkler Rough-in4/1/20194/2/20194/2/2019 2:27:18 PMPFAIL
Current tenting install will allow blow-in insulation to collect under piping, blocking the gap required for the radiant heat from the sheetrock, pocket between piping and sheetrock must be maintained for freeze prevention, cover is not approved.

Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
BLD19-00849 FIRE-Final Inspection4/1/20194/2/20194/2/2019 2:10:00 PMPFAIL
Provide correct suite numbers for each tenant spcae as shown on city approved drawings. Provide fire extinguisher with a current inspection tag and place in discussed location.

Call half hour before // Tom Phone #: ###-####
FIR19-00224 INSP-Final Inspection4/2/20194/2/20194/2/2019 1:51:15 PMPPASS
Final fire sprinkler inspection for scope of work complete.

Kyle Koepnick is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
BLD18-02200 FIRE-Final Inspection4/1/20194/2/20194/2/2019 12:16:23 PMAFAIL
Attempted to call point of contact listed, left a message on voicemail and gave 25 minutes for a return call, no return call was received, proceeded to next inspection.

Call for acess- Jacob Phone #: ###-####
FIR18-00633 INSP-Sprinkler Rough-in/Hydro4/1/20194/2/20194/2/2019 12:16:23 PMAFAIL
Attic heads do not match what was submitted to the city. Cover is not approved for any area on level 3 until head spacing for attic heads is figured out and city approved drawings reflect what is installed.

Kenny Caldwell is the contact. This inspection is requested to be a partial rough-in/hydro for the 4th floor. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
FIR18-00477 INSP-Supply line flush4/1/20194/2/20194/2/2019 10:52:56 AMADONE
Underground main line flush complete.

George Jess is the contact. This inspection is for an underground flush/hydro. Stacey with Suez should already be aware of this inspection. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
FIR18-00477 INSP-Sprinkler Rough-in/Hydro4/2/20194/2/20194/2/2019 10:52:31 AMADONE
Hyhdrostatic test for undergorund supply witnessed, no pressure loss observed.
FIR19-00187 INSP-Final Inspection3/29/20194/2/20194/2/2019 10:15:34 AMAPASS
Final fire alarm inspection for scope of work complete.

Phone #: ###-#### Inspection requested via web by Neal Timmerman
FIR19-00157 INSP-Final Inspection3/29/20194/2/20194/2/2019 9:57:30 AMAPASS
Final fire alarm inspection for scope of work complete.

Phone #: ###-#### Inspection requested via web by Neal Timmerman
FIR18-00938 INSP-Alarm Testing4/1/20194/2/20194/2/2019 9:26:29 AMPPASS
Final fire alarm inspection for area of work complete.

Dave Phone #: ###-####