FIR18-00901
| INSP-Conference | 4/2/2019 | 4/2/2019 | 4/2/2019 3:05:29 PM | P | DONE |
|
|
A second curb valve was installed after SUEZ valve to accomplish underground hydrostatic test, underground held 200psi for 2 hours as required by NFPA 13.
This is inspection to confirm our isolation of the underground from the Suez service and hydro test of UG. It can be completed during hydro test for overhead. We will be on site. Phone #: ###-#### Inspection requested via web by Jeff Packham
|
FIR18-00901
| INSP-Sprinkler Rough-in/Hydro | 4/2/2019 | 4/2/2019 | 4/2/2019 3:04:23 PM | P | DONE |
|
|
Hydrostatic test for underground supply and overhead fire sprinkler piping witnessed, no pressure loss observed.
Tom Phone #: ###-####
|
FIR19-00138
| INSP-Sprinkler Rough-in | 4/1/2019 | 4/2/2019 | 4/2/2019 2:27:18 PM | P | FAIL |
|
|
Current tenting install will allow blow-in insulation to collect under piping, blocking the gap required for the radiant heat from the sheetrock, pocket between piping and sheetrock must be maintained for freeze prevention, cover is not approved.
Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
BLD19-00849
| FIRE-Final Inspection | 4/1/2019 | 4/2/2019 | 4/2/2019 2:10:00 PM | P | FAIL |
|
|
Provide correct suite numbers for each tenant spcae as shown on city approved drawings. Provide fire extinguisher with a current inspection tag and place in discussed location.
Call half hour before // Tom Phone #: ###-####
|
FIR19-00224
| INSP-Final Inspection | 4/2/2019 | 4/2/2019 | 4/2/2019 1:51:15 PM | P | PASS |
|
|
Final fire sprinkler inspection for scope of work complete.
Kyle Koepnick is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
BLD18-02200
| FIRE-Final Inspection | 4/1/2019 | 4/2/2019 | 4/2/2019 12:16:23 PM | A | FAIL |
|
|
Attempted to call point of contact listed, left a message on voicemail and gave 25 minutes for a return call, no return call was received, proceeded to next inspection.
Call for acess- Jacob Phone #: ###-####
|
FIR18-00633
| INSP-Sprinkler Rough-in/Hydro | 4/1/2019 | 4/2/2019 | 4/2/2019 12:16:23 PM | A | FAIL |
|
|
Attic heads do not match what was submitted to the city. Cover is not approved for any area on level 3 until head spacing for attic heads is figured out and city approved drawings reflect what is installed.
Kenny Caldwell is the contact. This inspection is requested to be a partial rough-in/hydro for the 4th floor. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00477
| INSP-Supply line flush | 4/1/2019 | 4/2/2019 | 4/2/2019 10:52:56 AM | A | DONE |
|
|
Underground main line flush complete.
George Jess is the contact. This inspection is for an underground flush/hydro. Stacey with Suez should already be aware of this inspection. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00477
| INSP-Sprinkler Rough-in/Hydro | 4/2/2019 | 4/2/2019 | 4/2/2019 10:52:31 AM | A | DONE |
|
|
Hyhdrostatic test for undergorund supply witnessed, no pressure loss observed.
|
FIR19-00187
| INSP-Final Inspection | 3/29/2019 | 4/2/2019 | 4/2/2019 10:15:34 AM | A | PASS |
|
|
Final fire alarm inspection for scope of work complete.
Phone #: ###-#### Inspection requested via web by Neal Timmerman
|
FIR19-00157
| INSP-Final Inspection | 3/29/2019 | 4/2/2019 | 4/2/2019 9:57:30 AM | A | PASS |
|
|
Final fire alarm inspection for scope of work complete.
Phone #: ###-#### Inspection requested via web by Neal Timmerman
|
FIR18-00938
| INSP-Alarm Testing | 4/1/2019 | 4/2/2019 | 4/2/2019 9:26:29 AM | P | PASS |
|
|
Final fire alarm inspection for area of work complete.
Dave Phone #: ###-####
|