Inspections for the day of: Thursday, April 25, 2019.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR19-00271 INSP-Final Inspection4/24/20194/25/20194/25/2019 1:51:09 PMACANC
Inspection request cancelled per conversation with point of contact, inspection will be rescheduled for a later date by contractor.

Trying to final suppression along with alarm, thank you! Phone #: ###-#### Inspection requested via web by Don Kartchner
FIR18-00673 INSP-Alarm Testing4/24/20194/25/20194/25/2019 1:50:16 PMACANC
Fire alarm devices under a seperate permit, this request is cancelled.

Todd Phone #: ###-####
FIR19-00148 INSP-Sprinkler Rough-in4/25/20194/25/20194/25/2019 1:49:21 PMPPART
Rough to cover inspection for IBR and FDC piping complete, IBR and FDC piping under footing complete, approved for cover. Remaining underground supply piping to be installed at a later date.

Good morning! This is for an UG RTC today. Thank you for all of your help! Bryan is the contact for this. Have a great day! Phone #: ###-#### Inspection requested via web by Stan Beus
FIR18-00673 INSP-Final Inspection4/24/20194/25/20194/25/2019 1:46:59 PMAPART
Partial final inspection for overhead fire sprinklers complete, escutcheons are in place, no testing of fire alarm associated items due to fire alarm permit still in reviewed status.

Todd Phone #: ###-####
FIR17-00616 INSP-Final Inspection4/22/20194/25/20194/25/2019 11:32:50 AMAPASS
Final inspection for scope of work under this permit complete.

Steve Johnson (cell: ###-####) will meet you in the lobby of B26 Phone #: ###-#### Inspection requested via web by Steve Johnson
FIR19-00111 INSP-Sprinkler Rough-in4/24/20194/25/20194/25/2019 11:32:22 AMPFAIL
Need to verify that the dry flex heads used will be supported by the system calcs.

Contact Tyler Loomis ###-#### 30 min prior to RTC Insp start please.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
FIR18-00883 INSP-Supply line flush4/25/20194/25/20194/25/2019 11:31:39 AMADONE
Underground main line flush complete.
FIR19-00111 INSP-Supply line flush4/23/20194/25/20194/25/2019 11:31:10 AMACANC
Underground supply is on different permit, this request is cancelled.

Contact Tyler Loomis - ###-#### 30 min prior to Flush Insp. start please.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
FIR19-00240 INSP-Sprinkler Rough-in4/24/20194/25/20194/25/2019 9:35:14 AMAPASS
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, area of work approved for cover.

Phone #: ###-#### Inspection requested via web by Sam Ball
FIR18-00633 INSP-Sprinkler Rough-in4/24/20194/25/20194/25/2019 9:23:39 AMAPART
Rough to cover inspection for overhead fire sprinkler pipng partially complete, notated city approved drawings with pink and yellow highlighters areas approved for cover.

Kenny Caldwell is the contact. This rough-in is only for the 3rd and 4th floor. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus