FIR18-00267
| INSP-Final Inspection | 4/5/2019 | 4/9/2019 | 4/9/2019 4:09:07 PM | A | PART |
|
|
All fire alarm components associated with the fire sprinkler system has been tested, all devices tested satisfactorily.
THIS IS AN ALARM FINAL SO IT WILL TAKE A COUPLE HOURS. WE WILL CALL IN ANOTHER FINAL LATER WHEN ALL THE CEILING TILES ARE IN. Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|
BLD17-02757
| FIRE-Conference | 4/8/2019 | 4/9/2019 | 4/9/2019 4:07:18 PM | P | CANC |
|
|
Fire conference will be rescheduled per conversation with the point of contact, this request is cancelled.
Requesting 1st life safety walk; pre-final conference in conjunction with scheduled fire sprinkler final testing being performed by TVFP on same date/time at location. Superintendent - Jamal Nelson Phone #: ###-#### Inspection requested via web by Jamal Nelson
|
BLD19-00336
| FIRE-Conference | 4/9/2019 | 4/9/2019 | 4/9/2019 4:06:35 PM | P | DONE |
|
|
Fire conference complete, fire alarm notification throughout the building appears to be corridor notification and corridor only and the fire alarm is not monitored (Never has been based on the conversation with the tenants, which could have been code compliant on initial install). Based on my conversation with Ron Johnson the audio visual device in the "Little Rascals" room can be removed based on the fact the notification is in the corridor and this room is no longer part of a corridor. Stand-alone smoke detectors will need to be added per note number 7 of the Building fire code review comments to meet the requirement of each room having smoke detector coverage outside of the corridor. Door hardware will be changed to be code compliant and the blocked exit light will either be relocated or a new exit light will be added.
|
FIR18-00862
| INSP-Sprinkler Rough-in | 4/8/2019 | 4/9/2019 | 4/9/2019 1:50:02 PM | A | DONE |
|
|
24 hour air test for dry system complete.
Contact Tanner Loomis ###-#### 30 min Prior to 24 HR pressure Test start please, all Fees were PAID...04/08/19 AM...
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
FIR18-00862
| INSP-Sprinkler Rough-in/Hydro | 4/8/2019 | 4/9/2019 | 4/9/2019 1:49:36 PM | A | DONE |
|
|
Level 1 wet system hydro witnessed, no pressure loss observed.
Contact Tanner Loomis ###-#### 30 min Prior to Hydro Insp start please, all Fees were PAID...04/08/19 AM...
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
FIR17-00612
| INSP-Sprinkler Rough-in | 4/8/2019 | 4/9/2019 | 4/9/2019 1:48:58 PM | P | FAIL |
|
|
Rite Aid dry system lost 11 PSI during 24 hour air test.
The contact is Jon Beazor. This is for the 2nd part of the 24 hour air test. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00964
| INSP-Sprinkler Rough-in/Hydro | 4/8/2019 | 4/9/2019 | 4/9/2019 1:48:19 PM | A | DONE |
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed (Total of 9 systems), no pressure loss observed.
Please call Lonnie with time frame. Phone #: ###-#### Inspection requested via web by Jeff Packham
|
BLD19-00590
| FIRE-Final Inspection | 4/9/2019 | 4/9/2019 | 4/9/2019 9:43:23 AM | P | PASS |
|
|
Fire sprinkler inspection complete, no fire alarm modifications, fire extinguisher is placed with a current inspection tag. Final life fire safety inspection for area of work complete.
> Inspection requested via mobile web by Mike
|
FIR19-00227
| INSP-Final Inspection | 4/8/2019 | 4/9/2019 | 4/9/2019 9:42:27 AM | A | PASS |
|
|
Final fire sprinkler inspection for area of work complete.
Contact is John. Phone #: ###-#### Inspection requested via web by Sam Ball
|
FIR19-00227
| INSP-Sprinkler Rough-in | 4/8/2019 | 4/9/2019 | 4/9/2019 9:41:55 AM | A | PASS |
|
|
Rough to cover inspection for area of work complete, approved for cover.
Contact is John. Phone #: ###-#### Inspection requested via web by Sam Ball
|