Inspections for the day of: Friday, May 31, 2019.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR18-00826 INSP-Final Inspection5/31/20195/31/20195/31/2019 3:47:59 PMPPASS
Final underground supply inspection complete.
FIR18-00636 INSP-Final Inspection5/31/20195/31/20195/31/2019 3:47:48 PMPPASS
Final underground supply inspection complete.
FIR17-00508 INSP-Final Inspection5/31/20195/31/20195/31/2019 3:30:35 PMPFAIL
Wall mount speaker strobe is higher than 96 inches off of finish floor, move to code compliant elevation. Coordinate with audio contractor for audio shutdown in gym during active alarm.

late afternoon // Joe Phone #: ###-####
FIR19-00272 INSP-Final Inspection5/30/20195/31/20195/31/2019 3:30:13 PMPPASS
Final fire sprinkler inspection for area of work complete.

Phone #: ###-#### Inspection requested via web by Hunter Fillmore
FIR19-00272 INSP-Sprinkler Rough-in5/31/20195/31/20195/31/2019 1:38:47 PMPPASS
Rough to cover inspection for overhead fire sprinkler piping in area of work complete.
FIR18-00640 INSP-Final Inspection5/30/20195/31/20195/31/2019 1:09:27 PMAPASS
Final fire sprinkler inspection complete.

Mike Martin is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
FIR19-00288 INSP-Sprinkler Rough-in5/30/20195/31/20195/31/2019 10:30:33 AMAPASS
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, approved for cover.

Phone #: ###-#### Inspection requested via web by Sam Ball
FIR18-00640 INSP-Sprinkler Rough-in/Hydro5/30/20195/31/20195/31/2019 10:13:52 AMADONE
Hydrostatic test after install of dry uprights witnessed, no pressure loss observed.

Mike Martin is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
BLD17-04624 FIRE-Final Inspection5/30/20195/31/20195/31/2019 10:13:04 AMAPASS
Fire sprinkler inspection complete, fire al;arm inspection complete, fire extinguishers are placed with current inspection tags, knox box is located by fire sprinkler riser room. Final life fire safety inspection complete, fire alarms must be monitored after occupancy.

Fire / Life ; Safety Phone #: ###-#### Inspection requested via web by J.C. Murray
BLD17-04625 FIRE-Final Inspection5/30/20195/31/20195/31/2019 10:12:50 AMAPASS
Fire sprinkler inspection complete, fire al;arm inspection complete, fire extinguishers are placed with current inspection tags, knox box is located by fire sprinkler riser room. Final life fire safety inspection complete, fire alarms must be monitored after occupancy.

Fire / Life ; Safety Phone #: ###-#### Inspection requested via web by J.C. Murray
BLD17-04626 FIRE-Final Inspection5/30/20195/31/20195/31/2019 10:11:26 AMAPASS
Final life fire safety inspection completed 01APRIL2019.

Fire / Life ; safety Phone #: ###-#### Inspection requested via web by J.C. Murray