BLD17-00583
| FIRE-Final Inspection | 7/16/2018 | 7/16/2018 | 7/16/2018 1:39:47 PM | P | PART |
|
|
Life fire safety inspection complete for TCO phase 1 and phase 2
|
FIR18-00465
| INSP-Sprinkler Rough-in | 7/13/2018 | 7/16/2018 | 7/16/2018 1:36:27 PM | P | PASS |
|
|
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, approved for cover.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
BLD18-00545
| FIRE-Final Inspection | 7/16/2018 | 7/16/2018 | 7/16/2018 11:01:57 AM | P | PASS |
|
|
No fire sprinklers, smoke detection is stand-alone, fire extinguisher will be mounted in discussed location. Final life fire safety inspection for area of work complete.
Hans Phone #: ###-####
|
BLD18-02375
| FIRE-Final Inspection | 7/13/2018 | 7/16/2018 | 7/16/2018 8:55:10 AM | A | PASS |
|
|
Previously noted items have been completed, no fire sprinklers, no fire alarms, fire extinguisher is in place with a current inspection tag. Final life fire safety inspection complete.
call when on way out // Joe Phone #: ###-####
|