FIR19-00252
| INSP-Final Inspection | 7/16/2019 | 7/17/2019 | 7/17/2019 4:21:47 PM | P | PASS |
|
|
Final fire sprinkler inspection for scope of work complete.
Please call Clarence Phone #: ###-#### Inspection requested via web by Jessia Maxwell
|
FIR19-00263
| INSP-Sprinkler Rough-in | 7/16/2019 | 7/17/2019 | 7/17/2019 4:21:22 PM | P | PART |
|
|
Rough to cover inspection for overhead fire sprinkler piping on level 1B corridor and corridor soffits complete, level 1B corridor approved for cover. Tenting in place at time of inspection for level 2B southeast stairs, southeast stair hard-lid approved for cover. Dumpster room will need the tenting adjusted to cover T to dry sidewall heads, this area cannot be covered until tenting has been corrected and inspected for compliance.
Robert Chambers is the contact. He would like this inspection for the 1st floor area B. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
BLD19-00278
| FIRE-Conference | 7/16/2019 | 7/17/2019 | 7/17/2019 4:18:00 PM | A | DONE |
|
|
Inspection for insulation inside battered wall is complete, filled with non-combustible insulation, sprinkler heads are removed and deleted, approved for cover.
Exterior battered wall insulation north side of reception A101. Phone #: ###-#### Inspection requested via web by Corey Hockersmith
|
FIR19-00403
| INSP-Final Inspection | 7/16/2019 | 7/17/2019 | 7/17/2019 12:57:30 PM | P | FAIL |
|
|
Audible sound from speaker was very distorted, need to troubleshoot audible issue and schedule a re-inspect after issue is resolved.
Contact is Dirk. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
BLD18-04210
| FIRE-Final Inspection | 7/17/2019 | 7/17/2019 | 7/17/2019 12:56:21 PM | P | PASS |
|
|
FIre sprinkler inspection has been completed (Fire sprinkler modifications was completed under permit for Knitting Factory), no fire alarm modifications in area of work, fire exitnguishers are placed in common areas with current ispection tags. Final life fire safety inspection for area of work complete.
Tom Phone #: ###-####
|
FIR18-00510
| INSP-Sprinkler Rough-in/Hydro | 7/16/2019 | 7/17/2019 | 7/17/2019 12:52:52 PM | A | DONE |
|
|
Hydrostatic test for levels 4 and 5 witnessed, no pressure loss observed.
Hydro on 4th;5th floor. Phone #: ###-#### Inspection requested via web by Sam Ball
|
FIR18-00461
| INSP-Sprinkler Rough-in/Hydro | 7/16/2019 | 7/17/2019 | 7/17/2019 12:46:08 PM | A | DONE |
|
|
Hydrostatic test for overhead fire sprinkler piping on level 1 and standpipe witnessed, no pressure loss observed.
Hydro on first floor and standpipe Phone #: ###-#### Inspection requested via web by Sam Ball
|
BLD19-01405
| FIRE-Final Inspection | 7/16/2019 | 7/17/2019 | 7/17/2019 9:02:16 AM | A | PASS |
|
|
No fire sprinklers, no fire alarms, final life fire safety inspection for area of work complete.
Able Phone #: ###-####
|
BLD19-01408
| FIRE-Final Inspection | 7/16/2019 | 7/17/2019 | 7/17/2019 9:01:53 AM | A | PASS |
|
|
No fire sprinklers, no fire alarms, final life fire safety inspection for area of work complete.
Able Phone #: ###-####
|
FIR16-00819
| INSP-Final Inspection | 7/16/2019 | 7/17/2019 | 7/17/2019 8:33:03 AM | A | PASS |
|
|
Final inspection for underground supply complete.
Please call Clarence Phone #: ###-#### Inspection requested via web by Jessia Maxwell
|
FIR16-00819
| INSP-Sprinkler Rough-in/Hydro | 7/16/2019 | 7/17/2019 | 7/17/2019 8:32:34 AM | A | DONE |
|
|
Hydrostatic test for underground supply has been witnessed and completed.
Please call Clarence Phone #: ###-#### Inspection requested via web by Jessia Maxwell
|
FIR19-00263
| INSP-Sprinkler Rough-in | 7/16/2019 | 7/17/2019 | 7/16/2019 4:13:25 PM | P | CANC |
|
|
Robert Chambers is the contact. Thank you for your hard work! Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|