Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR18-00891 INSP-Sprinkler Rough-in/Hydro7/23/20197/26/20197/26/2019 2:27:37 PMPCANC
Could not complete hydrostatic test due to time constraints, hydro will need to be rescheduled.

Robert Chambers is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
FIR18-00889 INSP-Sprinkler Rough-in/Hydro7/23/20197/26/20197/26/2019 2:27:22 PMPCANC
Could not complete hydrostatic test due to time constraints, hydro will need to be rescheduled.

Robert Chambers is the contact. Thank you for your hard work!
Phone #: ###-#### Inspection requested via web by Stan Beus
FIR18-00891 INSP-Supply line flush7/23/20197/26/20197/26/2019 2:11:17 PMPDONE
Underground main line flush complete.

Robert Chambers is the contact. Stacey with Suez is aware of this flush, and will be there. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
FIR18-00889 INSP-Supply line flush7/23/20197/26/20197/26/2019 2:10:59 PMPDONE
Underground main line flush complete.

Robert Chambers is the contact. Stacey with Suez is aware of this inspection and will be there. Thank you for your hard work!
Phone #: ###-#### Inspection requested via web by Stan Beus
FIR19-00358 INSP-Sprinkler Rough-in/Hydro7/26/20197/26/20197/26/2019 2:10:11 PMPDONE
Hydrostatic test for newly installed piping witnessed, no pressure loss observed.

Mike Phone #: ###-####
FIR19-00019 INSP-Final Inspection7/26/20197/26/20197/26/2019 2:09:26 PMPPASS
Final fire sprinkler inspection complete.

Call Anthony before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
FIR19-00007 INSP-Final Inspection7/26/20197/26/20197/26/2019 1:58:03 PMPPASS
Final fire sprinkler inspection complete.

Call Anthony before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
BLD19-00591 FIRE-Final Inspection7/25/20197/26/20197/26/2019 10:23:15 AMPPASS
Fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection for area of work complete.

Jim Wellman Phone #: ###-#### Inspection requested via web by Jim Wellman
FIR19-00267 INSP-Final Inspection7/26/20197/26/20197/26/2019 10:21:39 AMPPASS
Final fire sprinkler inspection for area of work complete.

Contact Ken Orahood ###-#### 30 Min prior to Final Insp start please.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
FIR19-00485 INSP-Sprinkler Rough-in7/25/20197/26/20197/26/2019 10:12:46 AMAPASS
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, approved for cover. Any and all holes in the insulation will need to be filled if removed due to freeze protection requirements, sheetrock is not installed on the bottom of the trusses as shown on city approved drawings but attic protection is sufficient enough for combustible space coverage.

Troy Lowe is the contact for inspection. He is requesting a RTC inspection. Thank you for your help. Have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus
BLD19-02708 FIRE-Final Inspection7/25/20197/26/20197/26/2019 9:48:06 AMAPASS
No fire sprinkler modifications, no fire alarm modifications, fire extinguisher was placed with a current inspection tag, sticker on door will be changed to "Door to remain unlocked while building is Occupied" before building inspection. Final life fire safety inspection for area of work complete.

call for access- Kendra Phone #: ###-####
FIR19-00373 INSP-Sprinkler Rough-in7/25/20197/26/20197/26/2019 9:21:02 AMAPART
Rough to cover inspection for UBR complete, IBR approved for cover. Remaining underground to be installed at a later date.

Bryan Collins is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
FIR19-00168 INSP-Sprinkler Rough-in7/26/20197/26/20197/26/2019 9:19:08 AMAPART
Partial rough to cover inspectionfor overhead fire sprinkler piping in area of work complete, notated the city approved drawings with red ink areas approved for cover.

Phone #: ###-#### Inspection requested via web by Lonnie Greenfield
BLD19-00278 FIRE-Conference7/25/20197/26/20197/26/2019 8:48:30 AMADONE
Battered walls on the northeast and east side of building have been filled with non-combustible insulation, sprinkler heads have been deleted due to insulation install, approved for cover in tegards to fire sprinkler protection.

Battered wall insulation at living alcove B108 and outside units B115 and B118 (east side of building). Phone #: ###-#### Inspection requested via web by Corey Hockersmith
FIR19-00263 INSP-Sprinkler Rough-in7/26/20197/26/20197/26/2019 8:46:51 AMAPART
Tenting over sprinkler piping in the dumpster area has been corrected, dumpster area approved for cover.
FIR18-00001 INSP-Final Inspection7/25/20197/26/20197/26/2019 8:40:21 AMAPASS
Previously noted items that were notated on the city approved drawings has been corrected, final fire sprinkler inspection for area of work complete.

Clarence Phone #: ###-####
FIR19-00528 INSP-Final Inspection7/25/20197/26/20197/26/2019 8:30:27 AMAPASS
Final fire sprinkler inspection for area of work complete.

Contact Noemi Carrero ###-#### 30 min prior to Fire Final Insp start please.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
FIR19-00528 INSP-Sprinkler Rough-in7/25/20197/26/20197/26/2019 8:29:36 AMAPASS
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, area of work approved for cover.

Contact Noemi Carrero ###-#### 30 min prior to RTC insp start please

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank