Inspections for the day of: Tuesday, August 27, 2019.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD18-03442 FIRE-Conference8/27/20198/27/20198/27/2019 4:13:54 PMPDONE
Fire conference complete, discussed exit sign locations that would work for the low ceiling. Discussed needed items for life fire safety.
BLD18-03442 FIRE-Final Inspection8/27/20198/27/20198/27/2019 4:12:52 PMPCANC
Request was for a conference, not a final inspection. This request is cancelled.

Kelly Phone #: ###-####
BLD19-00703 FIRE-Final Inspection8/26/20198/27/20198/27/2019 2:47:56 PMPCANC
FIR permit for fire alarm \s needs to be finaled before life fire safety inspection can be completed, last fire alarm inspection resulted in a fail, this request is cancelled.

Mike Phone #: ###-####
BLD17-02261 FIRE-Conference8/27/20198/27/20198/27/2019 2:45:19 PMPDONE
Fire conference complete, discussed options for roof top access ladder arrangement.

Per Dave H Phone #: ###-####
FIR19-00004 INSP-Final Inspection8/27/20198/27/20198/27/2019 1:30:53 PMPPASS
Final fire sprinkler inspection complete, irrigation isolation not required on flow switch activation, irrigation on seperate non-potable water line and not part of the treated domestic water system.

Call before heading out, thank you Phone #: ###-#### Inspection requested via web by Anthony Minichiello
BLD19-01651 FIRE-Final Inspection8/27/20198/27/20198/27/2019 11:25:17 AMPPASS
Compliant door hardware has been installed on pocket doors, final life fire safety inspection is complete.

Jim,

The pulls are on the pocket doors. I will text you and Tony a picture.

Thanks,

Todd Phone #: ###-#### Inspection requested via web by Todd Kurns
BLD19-01546 FIRE-Final Inspection8/26/20198/27/20198/27/2019 11:22:48 AMAPASS
Previously noted item has been corrected, final life fire safety inspection for scope of work complete.

call rob Phone #: ###-#### Inspection requested via web by J.C. Murray
FIR18-00601 INSP-Supply line flush8/26/20198/27/20198/27/2019 10:36:48 AMADONE
Underground main line flush after pipe break complete.

Jon Beazer is the contact. Stacey with Suez has been contacted and is planning on this flush being around 9:30 AM. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
BLD19-00740 FIRE-Final Inspection8/26/20198/27/20198/27/2019 10:17:51 AMAPASS
Previously noted items have been corrected, fire sprinkler ispections are complete, no fire alarm modifications, fire extinguishers are in common areas with current inspection tags. Final life fire safety inspection for area of work complete.

TOM Phone #: ###-####
FIR18-00601 INSP-Final Inspection8/27/20198/27/20198/27/2019 9:28:00 AMPCANC
Jon Beazer is the contact. The final was done this morning, this is just the paper trail. Call Jon Beazer to answer any questions. Thank you for your hard work! Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
FIR19-00555 INSP-Final Inspection8/26/20198/27/20198/27/2019 8:44:37 AMAFAIL
Network interface between 8th street fire panel and Chase fire panel does not communicate on intial fire alarm, only time panels communicate on general fire is during a second fire alarm while 8th street fire panel is in alarm. Priority 2 alarm reports to chase panel but only have audio notification, no visual notification, troublshoot and repair to be code compliant.

firre alarmBrian Phone #: ###-####
FIR19-00237 INSP-Final Inspection8/23/20198/27/20198/27/2019 8:14:31 AMACANC
Contact Tyler Loomis ###-#### 30 min prior to Final Insp start please.

Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank