Inspections for the day of: Monday, September 10, 2018.
Number of inspections: 2
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR18-00420 INSP-Sprinkler Rough-in9/7/20189/10/20189/10/2018 12:00:00 AMAPASS
Forrest Inspection results-Rough-in inspection completed for overhead fire sprinkler work at the 2nd and 3rd floor shell and core areas. Approval for ceiling cover at the 2nd
floor restrooms. Contractor to revise over-spacing at four branch lines in the calc area on the 2nd floor as discussed. 3” main re-route appears
acceptable. Two branch lines at the 3rd floor are not yet installed due to stair construction underway.
Rough-In Inspection for 2nd & 3rd floors. Phone #: ###-#### >> Inspection requested via web by Sheldon Gray
BLD18-02142 FIRE-Final Inspection9/6/20189/10/20189/7/2018 12:00:00 AMADONE
No fire final required for U occupancy, open outside bike rack storageMike Jones Phone #: ###-####