FIR18-00420
| INSP-Sprinkler Rough-in | 9/7/2018 | 9/10/2018 | 9/10/2018 12:00:00 AM | A | PASS |
|
|
Forrest Inspection results-Rough-in inspection completed for overhead fire sprinkler work at the 2nd and 3rd floor shell and core areas. Approval for ceiling cover at the 2nd
floor restrooms. Contractor to revise over-spacing at four branch lines in the calc area on the 2nd floor as discussed. 3” main re-route appears
acceptable. Two branch lines at the 3rd floor are not yet installed due to stair construction underway.
Rough-In Inspection for 2nd & 3rd floors. Phone #: ###-#### >> Inspection requested via web by Sheldon Gray
|
BLD18-02142
| FIRE-Final Inspection | 9/6/2018 | 9/10/2018 | 9/7/2018 12:00:00 AM | A | DONE |
|
|
No fire final required for U occupancy, open outside bike rack storageMike Jones Phone #: ###-####
|