BLD18-03097
| BLD-Framing/Rough-in | 12/31/2018 | 12/31/2018 | 12/31/2018 4:58:34 PM | P | FAIL |
|
|
Per plans- (2) 9 1/2 LVL's required at bearing wall header, Master closet... Break in double top plates, bearing wall, Master closet... Need Engineering approval for A3 truss, bottom cord broken... Truss engineering packet frozen, not able to review any pages...
|
BLD18-03993
| BLD-Ceiling Grid Inspection | 12/31/2018 | 12/31/2018 | 12/31/2018 4:54:15 PM | P | PASS |
|
|
Tyler Phone #: ###-####
|
BLD18-03951
| BLD-Foundation | 12/28/2018 | 12/31/2018 | 12/31/2018 12:32:01 PM | A | PASS |
|
|
steam wall // Eric Phone #: ###-####
|
BLD18-02182
| BLD-Wall Bracing | 12/28/2018 | 12/31/2018 | 12/31/2018 12:31:49 PM | A | NR |
|
|
|
BLD18-03395
| BLD-Footing | 12/28/2018 | 12/31/2018 | 12/31/2018 9:51:21 AM | A | FAIL |
|
|
Per standard, soil, forms, and rebar to no less than 35F... Blanket and/or tent ...
|