BLD18-00637
| BLD-Other | 3/19/2019 | 3/19/2019 | 3/19/2019 5:00:16 PM | P | PASS |
|
|
Soffit
|
BLD18-00637
| BLD-Wall Bracing | 3/19/2019 | 3/19/2019 | 3/19/2019 5:00:09 PM | P | PASS |
|
|
Work in progress...
|
BLD18-02094
| BLD-Framing/Rough-in | 3/19/2019 | 3/19/2019 | 3/19/2019 4:59:31 PM | P | FAIL |
|
|
Provide propre hardware for anchor bolts and hold downs- see orange paint... Provide strap as indicated by framing note #9... As per plan note #10- In stall A34 clips and nail accordingly...
|
BLD18-02094
| BLD-Wall Bracing | 3/19/2019 | 3/19/2019 | 3/19/2019 4:57:35 PM | P | FAIL |
|
|
See Framing rough notes...
|
BLD18-03408
| BLD-Energy code compliance | 3/19/2019 | 3/19/2019 | 3/19/2019 4:57:02 PM | P | PASS |
|
|
|
BLD18-03408
| BLD-Framing/Rough-in | 3/19/2019 | 3/19/2019 | 3/19/2019 4:56:19 PM | P | PASS |
|
|
Corrections SAT...
|
BLD18-02154
| BLD-Final | 3/14/2019 | 3/19/2019 | 3/19/2019 4:55:13 PM | A | NR |
|
|
Need blower door test results posted...
|
BLD18-01524
| DOC - Permit Finaled | 3/19/2019 | 3/19/2019 | 3/19/2019 4:54:25 PM | P | PASS |
|
|
|
BLD18-00578
| BLD-Framing/Rough-in | 3/19/2019 | 3/19/2019 | 3/19/2019 12:57:33 PM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Chris Laraway
|
BLD18-03409
| BLD-Framing/Rough-in | 3/18/2019 | 3/19/2019 | 3/19/2019 12:56:04 PM | A | PASS |
|
|
Provide strap at break in double top plate at interior bearing wall... Beam to bear down to foundation, provide post as indicated on plans... Anchor bolts to be no more than 12" from ends on sill plates...
|
BLD18-03409
| BLD-Wall Bracing | 3/18/2019 | 3/19/2019 | 3/19/2019 12:42:52 PM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Gus Brandon
|
BLD18-00506
| DOC - Permit Finaled | 3/19/2019 | 3/19/2019 | 3/19/2019 8:23:04 AM | P | PASS |
|
|
|