BLD19-00603
| BLD-Energy code compliance | 5/22/2020 | 5/22/2020 | 5/22/2020 5:03:00 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Laz Ponce
|
BLD19-00602
| BLD-Energy code compliance | 5/22/2020 | 5/22/2020 | 5/22/2020 5:02:52 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Laz Ponce
|
BLD20-00916
| BLD-Foundation | 5/22/2020 | 5/22/2020 | 5/22/2020 5:02:42 PM | P | PASS |
|
|
Work in progress...
|
BLD20-00915
| BLD-Foundation | 5/22/2020 | 5/22/2020 | 5/22/2020 5:02:22 PM | P | PASS |
|
|
Work in progress...
|
BLD20-00914
| BLD-Foundation | 5/22/2020 | 5/22/2020 | 5/22/2020 5:02:00 PM | P | PASS |
|
|
Work in progress...
|
BLD20-00912
| BLD-Foundation | 5/22/2020 | 5/22/2020 | 5/22/2020 5:01:22 PM | P | PASS |
|
|
Work in progress...
|
BLD20-00031
| BLD-Conference | 5/22/2020 | 5/22/2020 | 5/22/2020 5:00:17 PM | P | CANC |
|
|
Jason Phone #: ###-####
|
BLD20-00262
| BLD-Wall cover | 5/22/2020 | 5/22/2020 | 5/22/2020 4:59:04 PM | P | PASS |
|
|
Jerry Phone #: ###-####
|
BLD19-04914
| BLD-Ceiling Grid Inspection | 5/21/2020 | 5/22/2020 | 5/22/2020 12:00:09 PM | A | PASS |
|
|
screened // Bubba Phone #: ###-####
|
BLD20-00093
| BLD-Foundation | 5/21/2020 | 5/22/2020 | 5/22/2020 12:00:00 PM | A | PASS |
|
|
*screened* Rebar - Steve Phone #: ###-####
|
BLD19-02853
| BLD-Footing | 5/21/2020 | 5/22/2020 | 5/22/2020 11:59:36 AM | A | PASS |
|
|
Work in progress....
|
BLD20-00088
| BLD-Framing/Rough-in | 5/21/2020 | 5/22/2020 | 5/22/2020 11:59:12 AM | A | PASS |
|
|
Framing corrections SAT... Insulation,ok... OK to cover...
|
BLD19-04013
| BLD-Wall Bracing | 5/21/2020 | 5/22/2020 | 5/22/2020 11:58:21 AM | A | PASS |
|
|
screened// exterior shear and fire caulk 2nd fix fir down// Pat Phone #: ###-####
|